I-70 Eastbound Resurfacing in Clear Creek County

Project Update

The I-70 Eastbound Resurfacing Project between the Eisenhower Memorial Tunnel and the US 40 Empire junction has resumed work for the spring of 2024

The remaining work includes paving and bridge deck repairs along eastbound I-70 at MP 218 (Herman Gulch), paving the eastbound on and off-ramps at Loveland Pass and Silver Plume, sign replacements, and finishing the guardrail replacement work.

Hours of operation will be from 6 p.m. to 8 a.m. Monday through Thursday nights as the weather allows.

About the Project:

The project will consist of resurfacing eastbound Interstate 70 from just outside the Eisenhower Johnson Memorial Tunnel (Mile Point 215.7) to the Georgetown on-ramp (MP 228.35), as well as a half-mile stretch of eastbound I-70 at the US 40 Empire Junction (Exit 232). Additionally, crews will replace damaged guardrails with new, safer ones.


Project Benefits

  • Creating a smooth roadway and placing new guardrails is a major element to the overall improvement of travel time reliability, safety, and mobility in the I-70 Mountain Corridor.


Work Schedule

  • Work will take place Sunday evening through Friday morning
  • Sunday evening through Monday morning: 9 p.m. to 8 a.m
  • Monday evening through Friday morning: 6 p.m. to 8 a.m.
  • There will not be lane closures during daytime hours, on weekends, or on holidays.
  • There will be a winter shutdown when the weather calls for it.
  • The project is expected to be completed fall 2024.

Traffic Impacts

  • Beginning in early August, there will be weeknight single-lane closures on I-70 eastbound, resulting in up to 30-minute delays.
  • Work/closure hours
    • Work will take place Sunday evening through Friday morning
    • Sunday evening through Monday morning: 9 p.m. to 8 a.m.
    • Monday evening through Friday morning: 6 p.m. to 8 a.m.
    • There will not be lane closures during daytime hours, on weekends, or on holidays.
  • Occasional overnight ramp closures will occur during paving
  • The speed limit will be reduced to 55 MPH through the work zone.
  • There will be 11-foot width restrictions on vehicles through the work zone.
  • Several other projects are happening in or near the Eisenhower Johnson
    Memorial tunnel and along the corridor. We encourage travelers to familiarize themselves with the I-70 mountain corridor project map and sign up for travel alerts at codot.gov/projects/i70mountaincorridor

Work this Week & Lane Closures I-70 EB Resurfacing

Project Facts

  • Construction Cost: $5 Million
  • Contractor: APC Construction Company
  • Timeline: August 2023 - October 2024
  • Location: Eastbound I-70 from just outside the Eisenhower Johnson Memorial Tunnel to the Georgetown on-ramp with a half-mile stretch of eastbound I-70 at the US 40 Empire
    Junction 
    • Nearest Town/City: Georgetown/Empire
    • Mile Point(s):  215.7 to 228.35, and Exit 232
    • County: Clear Creek

I-70 eastbound Clear Creek Resurfacing project map