Design-Build Process & Schedule
Update on December 19, 2019:
LAWRENCE CONSTRUCTION COMPANY and RS&H, Inc. were selected as the team representing the Best Value and has been identified as the apparent successful bidder for contract award for the US 550/160 Connection South Design Build Project. Read: Final Selection Announcement
Learn about the Design-Build Process
Proposed Design-Build Schedule
ScheduleThe following documents will be added as they become available throughout the project: |
||
Proposed Timeline | Events Processed | |
Issued: December 14, 2018 | Request for Letters of Interest | |
Deadline: January 31, 2019 | Letters of Interest Due | |
Issued: March 15, 2019 | Request for Qualifications (RFQ) | |
Deadline: April 26, 2019 | Statement of Qualifications Due (SOQ) | |
Issued: June 10, 2019 |
Short List Selection of Design-Build Teams Announced | |
Issued: June 10, 2019 | Draft Request for Proposal (RFP) | |
Issued: July 12, 2019 | Final RFP | |
Issued: August 22, 2019 |
RFP Addendum 1 | |
Deadline: October 30, 2019 |
Proposals Due | |
Announced: December 19, 2019 |
Selection of Design-Build Team LAWRENCE CONSTRUCTION CO./RS&H, Inc. |
|
Winter 2019/Spring 2020 |
Notice of Award |
|
Spring 2020 |
Contract Procurement of Design-Build Team (Notice to Proceed) |
|
Spring/Summer 2020 |
Construction Begins |
Previous D-B Process Activity
- August 2019
- View the documents associated with US 550/160 D-B RFP Addendum: RFP Addendum 1
- View the Final Request for Proposal documents: US 550/160 D-B Final RFP
- CDOT announces the three short listed teams: Press Release
- Contact the teams! Contact Information for the Three Firms
-
June 2019
CDOT and Connect2DOT co-hosted a Contractor Meet & Greet Event. Attendance was not mandatory to work on the US 550/US 160 Connection South project. We encourage you to reach out to the three “short listed” teams selected to prepare proposals to construct the Connection South Project. View contact information for the three teams: HERE.Below are the presentations and attendee list for the Meet & Greet event:
- On April 15, 2019, additions were made to the Request for Qualifications document: RFQ Addendum 1. Questions were submitted by teams and responses provided by the project team: RFQ General Questions and Responses. CDOT made available the revised Request for Qualifications contractor presentation with list of attendees: RFQ Contractor Briefing & Attendees.
- View additions made to the Request for Qualifications document: RFQ Addendum 1
- View the list of contractors who have submitted statements of interest: List of Contractors
- The CDOT Project Team hosted an informational meeting on Jan. 23, 2019 for contractors and teams intending to submit Letters of Interest. (Letters were due on Jan 31.) View the slide presentation, list of attendees and the questions and answers discussed at the meeting: Updated Contractor Briefing – 01-23-19
- CDOT announced the agency is accepting Letters of Interest (LOI) from companies, or teams of companies, interested in providing design-build services for the US 550-16- Connections South Project. Letters must have been received in the BidExpress System by 5:00 p.m. on January 31, 2019. Request for Letters of Interest