US 24 South of Minturn Resurfacing
About the Project:
The Colorado Department of Transportation with its contract partner United Companies will begin work on US Highway 24 south of Minturn in late April from MP 147 to MP 158.
Work on the project includes surface treatment, 2.5” HMA mill and overlay, pavement markings, and delineation on US 24 south of Minturn (MP 147 to MP 158). Once complete, the project will improve drivability for motorists and provide safer conditions for pedestrians and individuals using bicyclists.
Travelers to and from Leadville can avoid this and other nearby construction projects by using Colorado Highway 91 and Interstate 70.
Project Benefits
- Benefit 1
- Benefit 2
- Benefit 3
Work Schedule:
- Work will begin on US Highway 24 south of Minturn in late April. The project is scheduled for completion in late 2024.
- Work will occur during daytime hours, Monday through Friday.
- Single lane closures, double lane closures, and shoulder closures will take place within the work zone.
- Reduced speeds in the work zone.
- Plan ahead and expect short delays.
- Construction schedules are weather dependent.
- The project is scheduled for completion in late 2024
Traffic Impacts:
Motorists can expect the following impacts during the period of construction:
- Lane closures in both directions of <location>
- Traffic shifts on <location>
- Reduced speeds through the work zone
- Narrowed lanes and reduced shoulders
- Detour routes will be in place during certain work activities with approximately seven minutes and 10 miles added to travel times
- Width restrictions
- Signs will be posted to alert motorists to the closures and available detour routes
- Refer to COtrip.org for real-time travel conditions and road closures
Work this Week & Lane Closures US 24 Minturn Resurfacing
Project Facts
- Construction Cost: $11 Million
- Contractor: United Companies
- Timeline: April through December 2024
- Location: US 24
- Nearest Town/City: South of Minturn
- Mile Point(s): MP 147 to MP 158
- County: Eagle