US 160D Intersection Improvements in Mancos

About the Project

This is a sidewalk improvement project on US Highway 160D business route in downtown Mancos. Work includes over 1,000 linear feet of new sidewalk and installation of 64 Americans with Disabilities Act (ADA) compliant ramps for approximately eight blocks.

Along with new ADA curb ramps, there will be upgrades to driveway ramps and stormwater drainage systems within the work zone. At both Main Street and Mesa Street on the northeast and northwest corners, inlets will be replaced and stormwater pipes and drainage will receive upgrades.

Project Facts

  • Construction Cost: $2 million
  • Contractor: 
  • Timeline: April 2025 to September 2025
  • Location: US 160D 
    • Nearest Town/City: Mancos
    • Mile Point(s): MP 0.72 to MP 1.58
    • County: Montezuma
US 160 Mancos Pedestrian Improvements Map
The construction zone is in the heart of downtown Mancos on US 160D. It crosses multiple side streets including Main Street

Project Benefits

New sidewalks and ramps enhance accessibility for multi-modal travelers providing a smoother surface and other features that facilitate mobility.


Work Schedule

  • Daytime work hours range from 7 a.m. to 7 p.m., Monday through Friday

Traffic Impacts

Motorists can expect the following impacts during the period of construction:

  • Daytime work hours range from 7 a.m. to 7 p.m., Monday through Friday with work concluding in September
  • Motorists can expect shoulder closures and lane shifts
  • Pedestrians can expect sidewalk closures and detours
  • Refer to COtrip.org for real-time travel conditions and road closures