Regional BRT Corridors Implementation Timeline
- The Colfax Avenue BRT and CO-119 Diagonal Highway corridors
- Design phase - 2023 to mid 2024
- Construction phase - mid-2024 to mid-2026
- The Federal Boulevard BRT corridor
- Environmental and preliminary design phase - mid-2023 through 2024
- Design phase - early 2025 to mid-2026
- Construction phase - mid-2026 through 2028
- Funding is expected to be secured in 2024 and finalized in mid-2025
- The Colorado Boulevard BRT corridor
- Corridor study and conceptual design phase - mid-2023 to late 2024
- Environmental and preliminary design phase - early 2024 to mid-2025
- Design phase - mid-2025 through 2026
- Construction phase - early 2027 to late 2028
- The East Colfax Avenue Extension (I-225 to E-470) corridor
- Corridor study and conceptual design phase - mid-2024 to late 2025
- Environmental and preliminary design phase - early 2025 to mid-2026
- Design phase - mid-2026 through 2027
- Construction phase - early 2028 through 2029
- Funding is expected to be secured in mid-2025 and finalized in mid-2026
Schedule & Important Dates
- Planning and engineering, including evaluating environmental, social and economic impacts, will occur over the next few years.
- Construction on the corridors is scheduled to begin in 2024 and continue through 2030.