Southern Colorado Pavement Marking

About the Project:

Crews will remove existing pavement markings and add new striping and markings.

Project Maps:

Map of Southern Colorado Pavement Marking Location in Pueblo
Southern Colorado Pavement Marking Location in Pueblo

Map of Southern Colorado Pavement Marking Location in Colorado Springs
Southern Colorado Pavement Marking Location in Colorado Springs

Project Facts

  • Construction Cost: $2.49 Million
  • Contractor: Road Safe Traffic
  • Timeline: September 2024 to January 2025
  • Location: 
    CO 21, US 24, and US 85 near Colorado Springs 
    CO 45, CO 47, US 50 near Pueblo 
    • Nearest Town/City: Colorado Springs, Pueblo
    • Mile Point(s): 

      El Paso County:

      • CO 21, eastern Colorado Springs (Mile Point 141.74 to MP 154.11)
      • US 24, southeastern Colorado Springs (MP 303.41 to MP 310.87)
      • US 85, from Fountain north toward Colorado Springs (MP 127.77 to MP 137.04)

      Pueblo County:

      • CO 45, western Pueblo (MP 5.07 to MP 8.56)
      • CO 47, eastern Pueblo (MP 3 to MP 4.54)
      • US 50, Pueblo moving east to Avondale (MP 0 to MP 16.95)
    • County: El Paso, Huerfano and Pueblo



Project Benefits

The pavement striping and markings will make traveling conditions safer providing brighter, more visible lines.


Work Schedule:

  • Work will begin on CO 21 and US 24, crews will then move to the Pueblo locations (CO 45, CO 47 and US 50), and will finish the striping project on US 85 north of Fountain
  • Starting on Sept. 22, traffic impacts will take place Sunday through Thursday nights, from 7 p.m. to 7 a.m.

Traffic Impacts:

Motorists can expect the following impacts during the period of construction:

  • Various mobile lane closures will take place within the work zones with reduced speeds
  • Plan ahead and expect short delays
  • This is a swift moving, mobile operation; although work zones will only be in place for a few hours, motorists are urged to use caution and watch for heavy equipment
  • Through lanes and turn lanes may be temporarily closed to traffic causing brief travel delays
  • Travelers are discouraged from passing the striping truck and crossing over fresh paint, as this may damage a vehicle’s finish. Please drive with patience during striping operations
  • Construction schedules could change depending on the weather
  • Go to COtrip.org for the latest information on road conditions