Northeastern Colorado Signal Backplate Replacement
Project completed
About the Project
The Colorado Department of Transportation will begin work across the western portion of Region 4 to remove and replace the signal head backplates and visors.
Signal backplates are intended to expand the visibility of the signal by providing a consistent and controlled background of the signal. This helps to improve safety of the intersection in which the signal is located.
Project Facts
- Cost: $996,000
- Contractor: Sturgeon Electric Company
- Timeline: January 2021 to April 2021
- Location: Various highways in the following northeastern Colorado counties: Boulder, Larimer, Weld
Proposed Work Schedule
- Work will be performed Sunday through Thursday between the hours of 9 p.m. to 5 a.m.
-
Work is expected to be completed by April 2021, barring weather and/or shipment delays.
Traffic Impacts
- Single lane closures will be alternated while work is being done on the signal so traffic will have minimal impacts.