Northeastern Colorado Signal Backplate Replacement

Project completed

About the Project

The Colorado Department of Transportation will begin work across the western portion of Region 4 to remove and replace the signal head backplates and visors.

Signal backplates are intended to expand the visibility of the signal by providing a consistent and controlled background of the signal. This helps to improve safety of the intersection in which the signal is located.

Project Facts

  • Cost: $996,000
  • Contractor:  Sturgeon Electric Company
  • Timeline: January 2021 to April 2021
  • Location: Various highways in the following northeastern Colorado counties: Boulder, Larimer, Weld

Proposed Work Schedule

  • Work will be performed Sunday through Thursday between the hours of 9 p.m. to 5 a.m.  
  • Work is expected to be completed by April 2021, barring weather and/or shipment delays.


Traffic Impacts

  • Single lane closures will be alternated while work is being done on the signal so traffic will have minimal impacts.