I-76 Denver Metro Sign Replacement
About the Project:
Sign replacement work will take place along I-76, from the end of I-70 all the way to Lochbuie. The sign replacement project will happen over a 6-week period on I-76, Mile Point 0 to MP 26.
Project Benefits
- Safer, more efficient, and more user-friendly transportation systems, benefiting the general public by improving their travel experience and quality of life
- Reduced congestion and enhanced navigation
Work Schedule:
- Work will last approximately 1 month
- Work hours range from Sunday through Thursday from 6 p.m. to 6 a.m.
- Some overnight work is expected
Traffic Impacts:
Motorists can expect the following impacts during the period of construction:
- Vehicles will be reduced to a single-lane, alternating traffic intermittently in either direction, throughout the duration of the project
- Lane closures, guided by flaggers, will have up to 15-minute delays
- Refer to COtrip.org for real-time travel conditions and road closures
Work this Week & Lane Closures I-76 Denver Metro Sign Replacement
Project Facts
- Construction Cost: $328,000
- Contractor: Barricade Holdings LLC
- Timeline: May through June 2024
- Location: I-76
- Nearest Town/City: Arvada, Westminster, Commerce City, Thornton, and Brighton
- Mile Point(s): MP 0 to MP 26
- County: Adams