I-76 & Dahlia Emergency Bridge Repair

About the Project:

This project will repair the Dahlia Street bridge over I-76 after damage was caused when a tractor-trailer struck the edge of the bridge in March 2024.

Tractor-trailer rolled over after striking the Dahlia Street bridge over I-76 in March 2024
Tractor-trailer rolled over after striking the Dahlia Street bridge over I-76 in March 2024

Project Benefits

  • This project will repair the damaged bridge structure above I-76 and reopen both directions of traffic on Dahlia Street.

Work Schedule:

  • Work begins June 2 and continue until early July
  • Working hours are 7 p.m. to 5 a.m., 7 days a week

Traffic Impacts:

Motorists can expect the following impacts during the period of construction:

  • Single nighttime lane closures on I-76 from 7 p.m. to 5 a.m. through June
  • Continued restriction of northbound Dahlia Street traffic over I-76
  • A 36-hour closure of I-76 will be required to complete repairs in late June
  • Refer to COtrip.org for real-time travel conditions and road closures

Work this Week & Lane Closures
for I-76 & Dahlia Bridge Repair

Project Facts

  • Construction Cost: $1.25 million
  • Contractor: Kraemer NA
  • Timeline: June to July 2024
  • Location: Dahlia Street bridge over I-76
    • Nearest Town/City: Commerce City
    • Mile Point(s): 8.5
    • County: Adams