I-70 Rural Bridge Rehabilitation
About the Project
Bridge preventative maintenance work will occur just east of Limon on a 33-mile stretch from Limon to Flagler (Mile Points 362 to 394.5).
The first phase of the bridge preventative maintenance project will happen over eight months on I-70, beginning just east of Limon (MP 362) and moving east toward Flagler (MP 394.5).
The work will include:
- removing the existing concrete deck topping or hot mix asphalt
- receiving a polyester concrete overlay or waterproof membrane and hot mix asphalt overlay




Work this Week & Lane Closures:
I-70 & CR 36, I-70 & CR39 and I-70 & CR 43
I-70/Kyle Railroad & CR 48, I-70 & CR 3 and I-70 & CR 5
Project Facts
- Construction Cost: $5.2 Million
- Contractor: Structures, Inc.
- Timeline: March 2025 to November 2025
- Location: I-70
- Nearest Towns/Cities: Limon and Flagler
- Mile Point(s): MP 362 to 395
- Counties: Lincoln and Kit Carson
Project Benefits
The preventative maintenance work will feature benefits including:
- repairs to the existing bridge deck and expansion joints, improving the bridge's durability
- new overlays, including Polyester and Asphalt, designed to increase the lifetime of the bridge decks
Work Schedule
- Work will last approximately eight months
- Daytime work hours are from Monday through Friday, 30 minutes after sunrise (approximately 7 a.m.) to 30 minutes before sunset (approximately 5:30 p.m.)
Traffic Impacts
- Vehicles will be reduced to a single-lane, alternating traffic intermittently in either direction controlled by temporary traffic signals throughout the duration of the project
- Lane closures will have minor delays
- Speed limit will be reduced through the work zone. Speed Limit reduction may vary depending on the location of the structure
- Refer to COtrip.org for real-time travel conditions and road closures