Project Phasing
About the Project:
The project work zones are broken into 14 sections, with crews starting operations on the north side of I-70 at Pecos Street traveling westbound toward I-76, and transitioning to the south side of I-70 traveling east back toward Pecos Street. The sections include the following timeline:
Westbound:
- Pecos Street to Zuni Street: Spring 2024 to Summer 2024
- Zuni Street to Federal Boulevard: Spring 2024 to Fall 2024
- Federal Boulevard to Lowell Boulevard: Summer 2024 to Winter 2024
- Lowell Boulevard to Tennyson Street: Fall 2024 to Winter 2024
- Tennyson Street to Sheridan Boulevard: Winter 2024 to Spring 2025
- Sheridan Boulevard to Harlan Street: Spring 2025 to Summer 2025
- Harlan Street to I-76: Spring 2025 to Summer 2025
Eastbound:
- I-76 to Harlan Street: Summer 2025 to Winter 2025
- Harlan Street to Sheridan Boulevard: Summer 2025 to Fall 2025
- Sheridan Boulevard to Tennyson Street: Summer 2025 to Fall 2025
- Tennyson Street to Lowell Boulevard: Fall 2025 to Winter 2025
- Lowell Boulevard to Federal Boulevard: Winter 2025 to Spring 2026
- Federal Boulevard to Zuni Street: Winter 2025 to Summer 2026
- Zuni Street to Pecos Street: Spring 2026 to Fall 2026"