Project Phasing

About the Project:

Phased project timeline showing operations beginning at Pecos Street in the Spring of 2024, working on the north side of I-70 westward toward I-76, and transitioning to the south side of I-70 traveling east back toward Pecos Street. Crews will end in the fall of 2026.

The project work zones are broken into 14 sections, with crews starting operations on the north side of I-70 at Pecos Street traveling westbound toward I-76, and transitioning to the south side of I-70 traveling east back toward Pecos Street. The sections include the following timeline:

Westbound:

  • Pecos Street to Zuni Street: Spring 2024 to Summer 2024
  • Zuni Street to Federal Boulevard: Spring 2024 to Fall 2024
  • Federal Boulevard to Lowell Boulevard: Summer 2024 to Winter 2024
  • Lowell Boulevard to Tennyson Street: Fall 2024 to Winter 2024
  • Tennyson Street to Sheridan Boulevard: Winter 2024 to Spring 2025
  • Sheridan Boulevard to Harlan Street: Spring 2025 to Summer 2025
  • Harlan Street to I-76: Spring 2025 to Summer 2025

Eastbound:

  • I-76 to Harlan Street: Summer 2025 to Winter 2025
  • Harlan Street to Sheridan Boulevard: Summer 2025 to Fall 2025
  • Sheridan Boulevard to Tennyson Street: Summer 2025 to Fall 2025
  • Tennyson Street to Lowell Boulevard: Fall 2025 to Winter 2025
  • Lowell Boulevard to Federal Boulevard: Winter 2025 to Spring 2026
  • Federal Boulevard to Zuni Street: Winter 2025 to Summer 2026
  • Zuni Street to Pecos Street: Spring 2026 to Fall 2026"