The design concept developed during the National Environmental Policy Act phase and documented in the Environmental Assessment (EA) has been refined through a Construction Manager/General Contractor (CMGC) process. The refined design changes have to do with re-aligning parts of I-70 and the frontage roads due to geographic constraints in the canyon and construction safety/accessibility.
To access the most recent flyover rendering, please email the project team at [email protected] .
Geographic Section of I-70 Floyd Hill Project
The I-70 Floyd Hill Project will be built in three phases – East, Central and West. Overviews of each phase are below:
East Section (blue on the map) from County Road 65 to the bottom of Floyd Hill (near Johnson's Gulch)
Construction Start Date: July 2023.
Main Features of the East Section:
Construct a third travel lane on westbound I-70 from the top of Floyd Hill to connect with the existing Westbound Mountain Express Lane (which currently starts at the Veterans Memorial Tunnels). The new lane will be a tolled Express Lane; the two existing General Purpose Lanes will continue to be available for those that do not choose to use the Express Lane.
Install wildlife fencing between Exit 247 and Soda Creek Road (east of Exit 248).
Construct an eastbound I-70 climbing lane for heavy commercial or slow-moving vehicles from a new US 6 ramp to eastbound I-70 from the bottom of Floyd Hill to the Hyland Hills/Floyd Hill interchange at Homestead Road at the top of Floyd Hill.
Rendering of I-70 midway down Floyd Hill looking southeast
Rendering of I-70 midway down Floyd Hill looking northwest
Central Section (orange on the map) from the Middle of Floyd Hill to Hidden Valley/Central City Parkway
Expected Construction Start Date: Fall 2024
Main Features of the Central Section:
Continue the third travel lane (Express Lane) on westbound I-70
Replace the bridges at the bottom of Floyd Hill with new structures and alignment to improve safety and sight distance
Flatten curves on I-70 to improve safety and achieve a 55 MPH design speed
Construct a new frontage road connection between the US 6 and Hidden Valley/Central City Parkway interchanges
Relocate the US 6/I-70 on- and off-ramps to the Hidden Valley/Central City Parkway interchange (via the new frontage road connection)
Construct a new on-ramp to eastbound I-70 from the bottom of Floyd Hill/US 6, which will connect to the new eastbound I-70 climbing lane for heavy commercial or slow-moving vehicles
Reconstruct the Clear Creek Greenway trail from the bottom of Floyd Hill to County Road 314
Realign and restore portions of Clear Creek
Rendering of I-70 at the bottom of Floyd Hill from above
Rendering of I-70 east of Sawmill Gulch looking west
West Section (purple on the map) from Hidden Valley Interchange to Idaho Springs Exit 241
Construction Start Date: March 2024
Main features of the West Section:
Continue the third travel lane on westbound I-70 through the Veterans Memorial Tunnels to Exit 241
Flatten I-70 curves to improve safety and achieve a 55 MPH design speed
Rebuild the bridges over Clear Creek, just west of Hidden Valley
Resurface/reconstruct the Clear Creek Greenway trail from the Hidden Valley interchange to the Veterans Memorial Tunnels
Rendering of I-70 from the Veterans Memorial Tunnels looking east.