Floyd Hill Early Projects

Several early projects were identified during the Floyd Hill Environmental Assessment process that could be advanced prior to the main I-70 Floyd Hill project. These Early Projects include community and environmental mitigation elements that can be constructed ahead of the larger project to help improve safety and mobility. 

Map of the five  I-70 Floyd Hill Early Projects locations and titles, which include the US 40 Empire Wildlife Overpass, the US 40 and Homestead Road Roundabout, the US 40 and County Road 65 Roundabout, the Pegasus Transit Shuttle Stop and the I-70 and Genesee Wildlife Underpass.
I-70 Floyd Hill Early Projects Map

US 40 & Floyd Hill Roundabouts - Project Update

The US 40 & Floyd Hill Roundabouts project has reached substantial completion.
Work began in December 2022 and consisted of building two single-lane roundabouts at the intersections of US 40 and Homestead Road, and US 40 and County Road 65. This project was one of the I-70 Floyd Hill Early Projects advanced to improve traffic flow and safety.

In addition to the intersection reconstruction, crews made storm drain improvements, added lighting around the roundabouts, and bicycle-specific signage and pavement markings to enhance safety for cyclists. The roundabout location at US 40 and Homestead Road now has a bypass lane, allowing westbound US 40 travelers to bypass the roundabout if they don’t need to access the Floyd Hill neighborhood or I-70.

US 40 Homestead Finished Roundabouts
US 40 and Homestead Road Finished Roundabout

What this means for travelers:

  • When entering the roundabout, yield to traffic already navigating it.
  • When a safe gap is available, merge into the roundabout going
    counterclockwise.
  • As you travel the roundabout, pay attention to signage and merging vehicles. Once you safely enter the roundabout, you are allowed the right-of-way, meaning you don’t stop to allow other vehicles to enter. That being said, please pay attention to inexperienced roundabout travelers.
  • When you reach your desired exit point, signal to alert fellow travelers that you are exiting the roundabout, then safely move out of it.
  • Pay attention to cyclists or pedestrians navigating the roundabout and make note of pavement markings and signage.

For more information about safely navigating a roundabout, check out the Colorado Roundabouts educational video.

Wildlife Crossings

I-70 & Genesee Wildlife Underpass - Complete

Work has begun on the I-70 & Genesee Wildlife Underpass project, which includes construction a wildlife underpass at approximately I-70 Mile Point 254.5 which is in between the exits for Lookout Mountain and Genesee. This area has been identified as a hotspot for wildlife-vehicle collisions (WVC) and has the highest number of WVCs on I-70 east of the Eisenhower Johnson Memorial Tunnel. Wildlife fencing will be placed along both sides of I-70 (north and south) and extend from the I-70 and Genesee Exit (Exit 254) to the I-70 and Lookout Mountain Exit (Exit 256).

Scheduled:

  • Construction began in fall 2023 and was completed in June 2024

Traffic Impacts:

  • To build the wildlife underpass, crews will construct a temporary traffic shift on I-70 between Lookout Mountain and Genesee.
    Three lanes of travel will be maintained in both directions, but due to narrowed lanes motorists must use caution through the work zone.
  • The speed limit will be reduced to 55 MPH through the work zone.
  • There will be 11-foot width restrictions on vehicles through the work zone.
  • Impacts to traffic are expected to be minimal.
  • Once the project is complete, motorists will be traveling on the two new I-70 bridges with the wildlife underpass underneath.

Draft rendering of I-70 Genesee wildlife crossing

I-70 & Genesee Wildlife Underpass

US 40 Empire Wildlife Overpass - In Design

The US 40 Empire Wildlife Overpass project plans to construct a wildlife overpass on US 40 at approximately Mile Point 257 which is near the I-70 and US 40 Empire Interchange (I-70 Exit 232). The wildlife overpass will allow safe connectivity for the largest bighorn sheep herd in the state of Colorado as well as reducing wildlife-vehicle collisions. Wildlife fencing will be placed along both sides of US 40 (north and south) and extend to the town of Empire and south on County Road 257. This project also plans to apply rockfall mitigation designs and fencing adjacent to the wildlife crossing structure.

Estimated Schedule:

  • Construction Fall 2023-Spring 2025
  • Project Cost: Estimated $7M-$10M
  • Contractor: TBD

Rendering of US 40 Empire wildlife crossing

US 40 Empire Wildlife Overpass Rendering

Pegasus Transit Shuttle Stop – Current Construction

The Pegasus Transit Shuttle Stop will provide a carpooling and transit stop for the Pegasus shuttle transit service in the Evergreen/Floyd Hill area. 

Benefits of this shuttle service include:

  • Daily service between the Denver area and I-70 mountain corridor communities
  • Shuttle can use the Mountain Express Lanes west of Idaho Springs
  • Shuttle will be able to use the new Floyd Hill westbound Express Lane
  • Support for future electric vehicle charging at the Pegasus parking lot

Estimated Schedule:

  • Construction: July to December 2024
  • Project Cost: TBD
  • Contractor: Kraemer North America