I-70 Resurfacing from Chief Hosa to Colfax
|
|
Weekly Traffic Impacts & Work Update
|
|
|
Traffic Impacts - Feb. 23 to March 1
Please be advised of the following traffic impacts, restrictions, and planned work for next week for the I-70 Resurfacing from Chief Hosa to Colfax project in Jefferson County.
|
|
Overnight Traffic Impacts
Sunday, Feb. 23 to Thursday, Feb. 27 - Westbound & Eastbound I-70 - Morrison (Exit 259) to Lookout Mountain (Exit 256) - overnight lane closures
- Motorists can expect overnight single lane closures switching to double lane closures on westbound I-70, and single overnight lane closures on eastbound I-70 from the Morrison to Lookout Mountain exits
- On Sunday, the westbound I-70 single lane closure will be in place at 6 p.m,, swtiching to double lane closures at 8 p.m.
- Monday to Thursday, the single lane closures on westbound I-70 will begin at 7 p.m., switching to double lane closures at 9 p.m.
- Only single lane closures will exist on eastbound I-70 as needed for access to the median from 9 p.m. to 6 a.m., Sunday to Thursday
- All overnight closures will end by 6 a.m.
- During the overnight work and closures, traffic will be shifted into the open lane(s) and caution is advised
- Delays can be expected
- The closure limits for this weekly period are confined to Mile Point 259 to MP 256
- Speed reduction on westbound I-70 - speeds are reduced to 55 mph through the work zone on westbound I-70 from Morrison (Exit 259) to Lookout Mountain (Exit 256), with signs posted
- Work zone signs, message boards and construction devices are present alerting motorists to the work zone, lane closures and other restrictions
- Please obey speed limits and traffic signs and exercise caution
- Construction schedules are weather dependent and subject to change
Work includes installing and flowfilling concrete drainage pipe, and placing Class 6 road base.
|
|
Recent night view of crews pouring barrier along I-70 at Mile Point 257.
Photography by Anthony Lobato.
|
|
Drone views of installed median barrier on I-70 at MP 257 for drainage work.
Photography by Estate Media.
|
|
General Travel Impacts, Schedule & Scope of Work
- The project began in August 2024, with anticipated completion by late 2025
- Work will be performed in two shifts: 7 p.m. to 6 a.m. Sunday to Thursday and 7 a.m. to 7 p.m. Monday to Friday, except on holidays
- Hours will be modified during the winter months
- The project's purpose is to improve safety, mobility and travel time reliability along this 10-mile stretch of the I-70 mountain corridor
- Work includes milling and paving I-70 from the Chief Hosa to Colfax exits, replacing guardrail, repairing two bridge decks at the Morrison/CO 93 exit, installing storm drainage improvements, and adding variable speed limit signs and message boards on eastbound I-70 from Genesee Park (Exit 254) to Colfax (Exit 262)
- Overnight lane closures with traffic shifts will be taken Sunday to Thursday, except on holidays
- Daytime shoulder closures will be in place
- Occasional weekend overnight lane closures will exist, as needed
- Speed reduction on westbound I-70 - speeds are reduced to 55 mph through the work zone on westbound I-70 from Morrison (Exit 259) to Lookout Mountain (Exit 256), with signs posted
- Please obey speed limits and traffic signs and exercise caution
- Construction schedules are weather dependent and subject to change
- Visit COtrip.org for real-time road conditions and to plan your trips!
|
|
Nearby Project Impacts
I-70 Floyd Hill Project
- The I-70 Floyd Hill project, from west of Evergreen to eastern Idaho Springs, encompasses an eight mile section of the I-70 Mountain Corridor
- Ongoing impacts include overnight lane closures and shifts, traffic delays, and periodic ramp closures
- Weekday rock scaling and blasting operations will be taking place near Idaho Springs, with traffic holds and delays expected up to six times a day, from 9 a.m. to 3 p.m. Monday to Thursday, except on holidays
- The project limits extend from Beaver Brook (Exit 248) to Idaho Springs (Exit 241)
- Please refer to the official webpage via the link above for more information on this project's scope of work, schedule & traffic impacts
|
|
|
|
|