About the Project:

The Colorado Department of Transportation (CDOT) is working to complete the design for the interim mobility hub on I-25 and SH-7 located in Adams and Broomfield Counties. The interim transit improvements project will consist of constructing Bustang bus route slip ramps for both northbound off-ramp and southbound on-ramp, pedestrian bridge connecting the two bus slip ramps, sidewalks, and a park-n-ride lot in the southeast corner of the interchange.

Project Elements:

  • Bustang Bus Route slip ramps for both northbound off-ramp and southbound on-ramp
  • Bus shelters
  • Pedestrian Bridge
  • Park-n-Ride
  • Better sidewalk connectivity
  • Signal upgrades
  • Driver Relief Station
  • Bus shelters in the Park-n-Ride

Project Goals:

This project will provide parking for people who would connect to the CDOT Division of Transit and Rails Express Bus from Fort Collins to Denver and the reverse ride northbound to Fort Collins as well as provide increased access to multimodal transit options.

Project Location:

I-25 & CO 7 Interim Transit Improvements

This project is located on I-25 and SH-7, between milepost 228.5 and milepost 229.5 in Adams and Broomfield County.

Project Budget:

$16M for Design and Construction

Project Schedule for Design:

Fall of 2022 – Fall of 2023

Project Schedule for Construction:

Anticipated 2024 Construction


Work Schedule:

  • To be determined

Traffic Impacts:

  • To be determined

Project Facts

  • Cost: Pending
  • Contractor: Pending
  • Timeline: September 2022 - September 2023
  • Location: Pending