I-25 Ramp Signal Installation Across Colorado Springs
Project completed
Project Facts
- Goal: Make the road safer by providing a new surface, and upgrading infrastructure to current standards.
- Location: 12 on- and off-ramps/locations along a four-mile stretch of I-25 in Colorado Springs
- Cost: $3.3 million
- Timeline: July 2019 to Summer 2020
- Contractor: Main Electric
Project Overview
Crews on this project will install ramp-metering devices at 12 different locations along the I-25 corridor in Colorado Springs to help ease traffic flow. Specifically, work will take place at the following on- and off-ramps:
- South Academy Boulevard to northbound I-25
- West Bijou Street to northbound I-25
- Uintah Street to southbound I-25
- Uintah Street to northbound I-25
- Fontanero Street to southbound I-25
- Fontanero Street to northbound I-25
- Fillmore Street to southbound I-25
- Fillmore Street to northbound I-25
- Garden of the Gods Road to southbound I-25
- Garden of the Gods Road to northbound I-25
- South Rockrimmon Boulevard to southbound I-25
- Nevada Avenue to northbound I-25
Crews also will install electrical conduit, pull boxes, wiring, traffic pedestal poles with signal heads and signs.