US 36 Weekly Update

Crews are working on the finishing touches of the Eastbound US 36 Emergency Rebuild Project. This week crews will work to remove barrier from the roadway and install median plate covers on eastbound US 36.

Lane Closures

  • Wednesday, April 1, from 8 a.m. to 5 p.m., crews will require a closure of the right lane of eastbound US 36 to remove barrier from the roadway.
  • THIS WORK IS CANCELED DUE TO WEATHER - Thursday, April 2 and Friday, April 3, from 10 a.m. to 3 p.m., crews will require a closure of the far-left Express Lane on eastbound US 36 as crews install median cover plates. The left shoulder on westbound US 36 will also be closed.

This work is weather-dependent and subject to change.

Great news! By the end of the day today, March 19, 2020, crews anticipate opening the new, permanent bike path next to eastbound US 36. Bicyclists can still expect construction activity on and along the bike path. Thank you for your patience!

Crews are wrapping up work on the eastbound US 36 Emergency Rebuild Project. In the next couple of weeks, motorists can expect minor traffic impacts overnight as crews remove construction barrier. Bicyclists should be prepared to see flaggers on the bike path as crews finish pouring the last section of the permanent bike path. 

Due to winter weather through late 2019 and early 2020, final project completion is now expected in spring 2020.

permanent bike path next to eastbound US 36

Crews are continuing earthwork efforts under the US 36 bridge and completing finishing touches on the permanent bike path. Due to winter weather through late 2019 and early 2020, final project completion is now expected in spring 2020.

Lane Closures

Crews will close the right lane of eastbound US 36 for one night to move barrier so equipment can access the permanent bike path and grind pavement. This closure will begin overnight Sunday, March 8, at 8 p.m. and last through 5 a.m. 

For the most current information on when this closure is happening, watch overhead message boards along the US 36 corridor. 

This work is weather-dependent and subject to change.

Three lane configuration

Temporary Bike Path

A temporary bike path is open. Bicyclists should exercise caution while riding on the temporary bike path, because it is located near the active construction zone and is in close proximity to US 36 traffic. The temporary bike path is separated from traffic by a three-foot-tall concrete barrier.

Winter weather conditions prevented crews from installing an impact attenuator on eastbound US 36. Crews plan to install it next week. 

Crews are continuing earthwork efforts and finishing touches on the permanent bike path. Due to winter weather through late 2019 and early 2020, final project completion is now expected in spring 2020.

Lane Closures - THIS WORK WAS COMPLETED OVERNIGHT ON MONDAY, FEBRUARY 24.

Crews will close the right lane of easbound US 36 for one night to install an impact attenuator, which is a device intended to reduce damage to vehicles and motorists in the event of a crash. This is planned to happen overnight on Monday, Feb. 24, but may be rescheduled for another night (Tuesday through Friday) due to weather next week. The closure will begin at 8 p.m. and last through 5 a.m. To ensure the safety of bicyclists, crews will also close the temporary bike path. Both the lane and bike path closures are for one night only. 

For the most current information on when this closure is happening, watch overhead message boards along the US 36 corridor. 

This work is weather-dependent and subject to ch

Temporary Bike Path

A temporary bike path is open. Bicyclists should exercise caution while riding on the temporary bike path because it is located near the active construction zone and is in close proximity to US 36 traffic. The temporary bike path is separated from traffic by a three-foot-tall concrete barrier.

Please note during the closure above, the temporary bike path will be closed overnight. The temporary bike path will reopen once the above closure concludes.

Crews are continuing earthwork efforts and finishing touches on the permanent bike path. Due to winter weather through late 2019 and early 2020, final project completion is now expected in spring 2020.

Lane Closures

Crews will close the right lane of eastbound US 36 for one night to install an impact attenuator, which is a device intended to reduce damage to vehicles and motorists in the event of a crash. This work will happen overnight either on Monday, Tuesday or Wednesday, depending on weather. The closure will begin at 8 p.m. and last through 5 a.m. To ensure the safety of bicyclists, crews will also close the temporary bike path. Both the lane and bike path closures are for one night only. 

For the most current information on when this closure is happening, watch overhead message boards along the US 36 corridor. 

This work is weather-dependent and subject to change.

Three lane configuration

Temporary Bike Path

A temporary bike path is open. Bicyclists should exercise caution while riding on the temporary bike path because it is located near the active construction zone and is in close proximity to US 36 traffic. The temporary bike path is separated from traffic by a three-foot-tall concrete barrier.

Please note during the closure above, the temporary bike path will be closed overnight. The temporary bike path will reopen once the above closure concludes.

This week, crews finished all work on the median barrier and lighting. Crews have also finished all planned lane closures for 2019. The next planned lane closures will be in mid-January. Until then, crews plan to continue earthwork and finishing touches on the permanent bike path.

Due to extreme winter weather during October, November and December, final project completion is now expected in January 2020.

There are no planned lane closures through the rest of December and most of January. Email updates will begin again when there are planned travel impacts.

For any additional information, please check the website (www.codot.gov/projects/eb-us-36-emergencyrepairs). Have a safe and happy holiday season!

Ongoing Work

Work on the permanent bike path and fence is expected to last into January.

Weekly Update 191213

Temporary Bike Path

A temporary bike path is open. Bicyclists should exercise caution while riding on the temporary bike path because it is located near the active construction zone and is in close proximity to US 36 traffic. The temporary bike path separated from traffic by a three-foot-tall concrete barrier.

Crews finished placing precast panels on the wall this week. Additional work on the wall, permanent bike path and fence is expected to last through December. Some overnight lane closures will be necessary as work continues. All work schedules are weather-dependent.

Weekly Updated 191206.png

Upcoming Overnight Lane Closures 

  • 8 p.m. to 5 a.m., overnight Sunday, Dec. 8 and Monday, Dec. 9
    • Along eastbound US 36, between Wadsworth and Church Ranch boulevards, the Express Lane and the left general-purpose lane will be closed to remove median barrier.
  • 10 p.m. to 6 a.m., overnight Monday, Dec. 9
    • Along westbound US 36, between Church Ranch and Wadsworth boulevards, the Express Lane and the left general-purpose lane will be closed to install standing light poles.

Upcoming Daytime Lane Closure

  • 9 a.m. to 3 p.m., Thursday, Dec. 12
    • Along eastbound US 36, between Wadsworth and Church Ranch boulevards, the right shoulder will be closed as crews install lighting in the area.

Ongoing Work

Additional work on the wall, permanent bike path, and fence is expected to last through December. This includes:

  • Reconstruction of median barrier and lighting (this will require nighttime lane closures)
  • Permanent bike path configuration and fence barrier separation from the highway

Temporary Bike Path

A temporary bike path is open. Bicyclists should exercise caution while riding on the temporary bike path because it is located near the active construction zone and is in close proximity to US 36 traffic. The temporary bike path separated from traffic by a three-foot-tall concrete barrier.

Bicyclists can expect intermittent closures of the bike path through November so construction crews can continue to safely work on the side of the wall.

Crews continue to place precast panels on the wall this week. Last Friday, crews had approximately 80% of the precast panels placed on the side of the retaining wall. Work on the wall, permanent bike path and fence is expected to last through December. Some overnight lane closures will be necessary as work continues. All work schedules are weather-dependent.

Upcoming Overnight Lane Closures 

  • 8 p.m. to 5 a.m., overnight Tuesday, Dec. 3 
    • Along eastbound US 36, between Wadsworth and Church Ranch boulevards, the Express Lane and the left general-purpose lane will be closed for median barrier work.

****All overnight lane closures for Thursday, Dec. 5 are canceled due to weather. 

  • 11 p.m. to 5 a.m., overnight Thursday, Dec. 5
    • Along eastbound US 36, between Wadsworth and Church Ranch boulevards, the Express Lane and the left general-purpose lane will be closed for light pole installation.
  • 10 p.m. to 6 a.m., overnight Thursday, Dec. 5
    • Along westbound US 36, between Church Ranch and Wadsworth boulevards, the Express Lane and the left general-purpose lane will be closed for barrier removal.

Ongoing Work

Additional work on the wall, permanent bike path, and fence is expected to last through December. This includes:

  • Reconstruction of median barrier and lighting (this will require nighttime lane closures)
  • Placement of 77 wall panels that form the façade of the retaining wall
  • Permanent bike path configuration and fence barrier separation from the highway

Weekly Update 11-15-19

Temporary Bike Path

A temporary bike path is open. Bicyclists should exercise caution while riding on the temporary bike path because it is located near the active construction zone and is in close proximity to US 36 traffic. The temporary bike path separated from traffic by a three-foot-tall concrete barrier.

Bicyclists can expect intermittent closures of the bike path through November so construction crews can continue to safely work on the side of the wall. 

US 36 has been restored to its original configuration with three lanes in each direction. Crews continue to place precast panels on the wall this week. By Friday, crews expect to have 90% of the precast panels placed on the side of the retaining wall. Work on the wall, permanent bike path and fence is expected to last through December. Some overnight lane closures will be necessary as work continues. All work schedules are weather-dependent.

In observance of the holiday weekend, there will be no planned traffic impacts beginning at noon on Wednesday, Nov. 27, until 8 a.m. Monday, Dec. 2. 

Upcoming Overnight Lane Closures 

NOTE: All lane closures listed below have been cancelled due to weather

  • 8 p.m. to 5 a.m., overnight Monday, Nov. 25
    • Along eastbound US 36, between Wadsworth and Church Ranch boulevards, the right lane will be closed so crews can install standing light poles and remove temporary barrier.
  • 8 p.m. to 5 a.m., overnight Tuesday, Nov. 26
    • Along westbound US 36, between Church Ranch and Wadsworth boulevards, the right lane will be closed so crews can remove temporary barrier.

Ongoing Work

Additional work on the wall, permanent bike path, and fence is expected to last through December. This includes:

  • Reconstruction of median barrier and lighting (this will require nighttime lane closures)
  • Placement of 77 wall panels that form the façade of the retaining wall
  • Permanent bike path configuration and fence barrier separation from the highway

Weekly Update 11-15-19

Temporary Bike Path

A temporary bike path is open. Bicyclists should exercise caution while riding on the temporary bike path because it is located near the active construction zone and is in close proximity to US 36 traffic. The temporary bike path separated from traffic by a three-foot-tall concrete barrier.

Bicyclists can expect intermittent closures of the bike path through November so construction crews can continue to safely work on the side of the wall. 

US 36 has been restored to its original configuration with three lanes in each direction. Crews began placing precast panels on the wall this week. Crews have placed about 10 of 77 precast panels on the side of the retaining wall. Work on the wall, permanent bike path and fence is expected to last through December. Some overnight lane closures will be necessary as work continues. All work schedules are weather-dependent.

Upcoming Overnight Lane Closures 

  • 8 p.m. to 5 a.m., overnight each night Sunday, Nov. 17, through Tuesday, Nov. 19 
    • Along eastbound US 36, between Wadsworth and Church Ranch boulevards, the Express Lane and left general purpose lane will be closed so crews can work on median barrier.

Weekly Update 11-15-19

Ongoing Work

Additional work on the wall, permanent bike path, and fence is expected to last through December. This includes:

  • Reconstruction of median barrier and lighting (this will require nighttime lane closures)
  • Placement of 77 wall panels that form the façade of the retaining wall
  • Permanent bike path configuration and fence barrier separation from the highway

Temporary Bike Path

A temporary bike path is open. Bicyclists should exercise caution while riding on the temporary bike path because it is located near the active construction zone and is in close proximity to US 36 traffic. The temporary bike path separated from traffic by a three-foot-tall concrete barrier.

Bicyclists can expect intermittent closures of the bike path through November so construction crews can continue to safely work on the side of the wall. 

US 36 has been restored to its original configuration with three lanes in each direction. Work on the wall, permanent bike path, and fence is expected to last through December. Some overnight lane closures will be necessary as work continues. All work schedules are weather-dependent.

Upcoming Overnight Lane Closures

  • 8 p.m. to 5 a.m., overnight each night Sunday, Nov. 10 and Tuesday, Nov. 12 through Friday, Nov. 15
    • Along eastbound US 36, between Wadsworth and Church Ranch boulevards, the Express Lane and left general purpose lane will be closed so crews can work on median barrier.

US 36 Eastbound Lane Graphic

Ongoing Work

Additional work on the wall, permanent bike path, and fence is expected to last through December. This includes:

  • Reconstruction of median barrier and lighting (this will require nighttime lane closures)
  • Placement of 77 wall panels that form the façade of the retaining wall
  • Permanent bike path configuration and fence barrier separation from the highway

Temporary Bike Path

A temporary bike path is open. Bicyclists should exercise caution while riding on the temporary bike path because it is located near the active construction zone and is in close proximity to US 36 traffic. The temporary bike path separated from traffic by a three-foot-tall concrete barrier.

Bicyclists can expect intermittent closures of the bike path through November so construction crews can continue to safely work on the side of the wall. 

US 36 has been restored to its original configuration with three lanes in each direction. Work on the wall, permanent bike path, and fence is expected to last through December. Some overnight lane closures will be necessary as work continues. All work schedules are weather-dependent.

Upcoming Overnight Lane Closures

  • 8 p.m. to 5 a.m., overnight Monday, Nov. 4 and Tuesday, Nov. 5
    • Along eastbound US 36, the Express Lane and left general purpose lane will be closed so crews can install caissons for new lights.

US 36 Eastbound Lane Graphic

Ongoing Work

Additional work on the wall, permanent bike path, and fence is expected to last through December. This includes:

  • Reconstruction of median barrier and lighting (this will require nighttime lane closures)
  • Placement of 77 wall panels that form the façade of the retaining wall
  • Permanent bike path configuration and fence barrier separation from the highway

Temporary Bike Path

A temporary bike path is now open. Bicyclists should exercise caution while riding on the temporary bike path because it is located near the active construction zone and is in close proximity to US 36 traffic. The temporary bike path separated from traffic by a three-foot-tall concrete barrier. Bicyclists can expect intermittent closures of the bike path through November so construction crews can continue to safely work on the side of the wall.

US 36 has been restored to its original configuration as of Friday, Oct. 4, with three lanes in each direction. Work on the wall, permanent bike path, and fence is expected to last through December. Some overnight lane closures will be necessary as work continues. All work schedules are weather-dependent.

Upcoming Overnight Lane Closures

  • 10 p.m., Saturday, Oct. 19, through 7 a.m., Sunday, Oct. 20
    • Single-lane closure of the far-right lane on eastbound US 36 for the installation of glare screen on the bike path barrier. The temporary bike path will be closed during the installation of glare screen starting at 8 p.m., Saturday, Oct. 19.
  • 10 p.m., Sunday, Oct. 20, through 5 a.m., Monday, Oct. 21 (overnight)
    • Double-lane closure of the two left lanes, including the Express Lane, on eastbound US 36 for roadway striping.
  • 10 p.m., Monday, Oct. 21, through 5 a.m., Tuesday, Oct. 22 (overnight)
    • Double-lane closure of the two left lanes, including the Express Lane, on eastbound US 36 for roadway striping.
  • 8 p.m., Tuesday, Oct. 22, through 5 a.m., Wednesday, Oct. 23 (overnight and if needed due to weather)
    • Double-lane closure of the two left lanes, including the Express Lane, on eastbound US 36 for roadway striping

US 36 Eastbound Lane Graphic

Ongoing Work

Additional work on the wall, permanent bike path, and fence is expected to last through December. This includes:

  • Reconstruction of median barrier and lighting (this will require nighttime lane closures)
  • Placement of 77 wall panels that form the façade of the retaining wall.
  • Permanent bike path configuration and fence barrier separation from the highway.

Temporary Bike Path

Temporary bike path is now open. Bicyclists should exercise caution while riding on the temporary bike path because it is located near the active construction zone and is in close proximity to US 36 traffic. The temporary bike path separated from traffic by a three-foot-tall concrete barrier.

Bicyclists can expect intermittent closures of the bike path through November so construction crews can continue to safely work on the side of the wall.

Schedule Change Due to Weather

Due to the precipitation expected overnight Tuesday, Oct. 1, the decision has been made to push back the US 36 traffic switch one day. The overnight lane closures will now take place on Wednesday and Thursday nights, Oct. 2 and 3. This decision was made because the project needs to have dry pavement conditions in order to safely and effectively stripe the roadway.

By Friday morning’s commute (Oct. 4), crews anticipate having US 36 back into its original three-lane configuration with Express Lanes open and operational at that time. The following activities are expected to restore US 36 lanes back into its original configuration. Remember: work is weather-dependent.

Lane Closures

  • 8 p.m. Wednesday, Oct. 2, through 5 a.m. Thursday, Oct. 3
    • Single-lane closure of both eastbound and westbound US 36 so crews can restripe and move barrier
  • 8 p.m. Thursday, Oct. 3, through 5 a.m. Friday, Oct. 4
    • Single-lane closure of both eastbound and westbound US 36 so crews can finish restriping the roadway into its original configuration and reset median barrier.

Traffic Changes

In addition to the above lane closures, motorists can expect the following traffic changes:

  • Thursday morning at 5 a.m.
    • Two eastbound lanes of US 36 will be restored to its original configuration.
    • The bike path will be opened into a temporary configuration shortly after.
  • Friday morning at 5 a.m.
    • All lanes of US 36, both eastbound and westbound, will be opened in their original configuration.
    • Express Lane tolling will begin at 5 a.m. in both directions.

US 36 Eastbound Lane Graphic

Ongoing Work

The No. 1 priority for CDOT and Kraemer North America has been to return eastbound US 36 to its original traffic pattern with three lanes in each direction. This is expected in full by the morning commute on Friday, Oct. 4.

Additional work on the wall, final bike path, and fence are expected to last through December. This includes:

  • Reconstruction of median barrier and lighting (this will require nighttime lane closures)
  • Installation of concrete caissons, which will be drilled down to bedrock to ensure stability of the wall. This work will be completed this week.
  • Placement of 77 wall panels that form the façade of the retaining wall.
  • Final bike path configuration and fence barrier separation from the highway.

With the geofoam, load distribution slab, and concrete pavement in place, three lanes of eastbound US 36 can be safely opened while the remaining work on the wall is on-going.

Temporary Bike Path

Crews plan to re-open the bike path into a temporary configuration by Thursday morning, Oct. 3.

Bicyclists should exercise caution while riding through this area because the temporary bike path is located near the active construction zone and is in close proximity to US 36 traffic, separated by three feet tall concrete barrier.

Once the temporary bike path is open, bicyclists can expect intermittent closures of the bike path through November so construction crews can continue to safely work on the side of the wall.

Crews have been working hard to rebuild the eastbound US 36 wall and achieved a major milestone this week. Geofoam installation is complete – all 6,000 blocks have been placed. Crews continue installing concrete caissons, which will be drilled down to bedrock to ensure stability of the wall foundation. Approximately 70 of the 141 concrete caissons have been drilled so far.

By Friday, Sept. 20, crews will complete the final load distribution slab pour. Crews are expected to start pouring the concrete pavement for the roadway itself next week.

Crews are still on track to open the eastbound US 36 lanes by early October.

US 36 - 100% Geofoam Installed

What is Geofoam?

The rebuilt section of US 36 will include drilling concrete caissons down into the bedrock and placing a material called geofoam behind the retaining wall in place of the existing backfill. Geofoam is a lightweight backfill that has been used effectively in similar situations with settlement. Since geofoam is lightweight, it reduces pressure and stress to the underlying soil. It is also very strong, which means it can safely support highway loading and also lead to improved slope stability. Of the different options considered, this option provides the best factor of safety. The geofoam is being produced by Insulfoam, which has a local plant in Aurora.

Construction Timeframe

The No. 1 priority for CDOT and Kraemer North America has been to return eastbound US 36 to its original traffic pattern with three lanes in each direction. This is expected in October. In addition to opening traffic to the original alignment, crews will install a temporary bike path that will open to the public in October. Additional work on the wall, final bike path, and fence is expected to last through December.

The project team is working around-the-clock to restore the road to its original configuration.

Alternate Routes Available

Thank you for driving safely and being patient through the work zone. For estimated commute time, visit COtrip.org. Or, consider an alternate route:

  • Take I-25 north to 120th Avenue (CO 128 and US 287) and take that west to get back on westbound US 36 at Broomfield.
  • Similarly, you could take Federal Boulevard (US 287) north to 120th Avenue and take that same route to get back to US 36 westbound.
  • Take Wadsworth (CO 121) north all the way to westbound US 36 at Broomfield.
  • Take CO Highway 93 from Golden up to Boulder.

Site Surveys

continues to be isolated to one area. There continues to be no movement on the westbound side. It is stable and safe for traffic.

Two travel lanes remain open in both directions.

The site is being monitored at all times to ensure continued safety for the traveling public.

Speed Up Your Commute

During the rebuild project on US 36, there will be increased congestion along the corridor. To alleviate congestion issues and reduce your commute time, there are alternatives to driving alone. Using the My Way to Go network, you can connect with carpools or vanpools along the US 36 corridor. Not only will this take cars off the road, it’s great for your wallet and the environment. Learn more about carpooling.

Vanpools are a great option for commuters who travel more than 15 miles to work one- way. Passengers share the ride in a vehicle — which, contrary to the name, isn’t always a van — that seats 5-15 people. Participants pay a monthly fee that covers the cost of fuel, insurance and vehicle maintenance. For a limited time, receive $20 a month off the cost of vanpooling through the VanCool program

US 36 is also home to the Flatiron Flyer, RTD’s first Bus Rapid Transit (BRT) service to connect Boulder to Denver. The Flatiron Flyer offers commuters a reliable ride every 4 to 15 minutes during peak hours and every 15 minutes off-peak, Monday through Friday. 2019 Flatiron Flyer fares: $3 local three-hour pass and $5.25 regional three-hour pass. Click here to learn more about the Flatiron Flyer service.

Want to learn more? Commuting Solutions is the go-to resource for transportation solutions in the northwest metro region, spanning from Westminster to Longmont, that seeks to reduce traffic congestion, improve air quality and improve the lives of commuters in our region. Visit our website at commutingsolutions.org or email us at [email protected] for help finding your best commute.

Crews have been working around-the-clock to rebuild the eastbound US 36 wall. Geofoam installation continues, and approximately 4,500 geofoam blocks have been placed. More than 6,000 blocks of geofoam are expected to be used during this rebuild project. Crews have also started installing concrete caissons, which will be drilled down to bedrock to ensure stability of the wall foundation. Approximately 50 of the 141 concrete caissons have been drilled so far.

Crews have also begun tying rebar on the load distribution slab and have completed the first pour. This concrete slab will distribute weight evenly along the geofoam blocks.

75% Geofoam Complete

What is Geofoam?

The rebuilt section of US 36 will include drilling concrete caissons down into the bedrock and placing a material called geofoam behind the retaining wall in place of the existing backfill. Geofoam is a lightweight backfill that has been used effectively in similar situations with settlement. Since geofoam is lightweight, it reduces pressure and stress to the underlying soil. It is also very strong, which means it can safely support highway loading and also lead to improved slope stability. Of the different options considered, this option provides the best factor of safety. The geofoam is being produced by Insulfoam, which has a local plant in Aurora.

Construction Timeframe

The No. 1 priority for CDOT and Kraemer North America has been to return eastbound US 36 to its original traffic pattern with three lanes in each direction. This is expected in October. In addition to opening traffic to the original alignment, crews will install a temporary bike path that will open to the public in October. Additional work on the wall, final bike path, and fence is expected to last through December.

Crews have been working every day to repair the damaged wall. All the geofoam has been delivered to the site, and the project team is working around-the-clock to restore the road to its original configuration.

Alternate Routes Available

Thank you for driving safely and being patient through the work zone. For estimated commute time, visit COtrip.org. Or, consider an alternate route:

  • Take I-25 north to 120th Avenue (CO 128 and US 287) and take that west to get back on westbound US 36 at Broomfield.
  • Similarly, you could take Federal Boulevard (US 287) north to 120th Avenue and take that same route to get back to US 36 westbound.
  • Take Wadsworth (CO 121) north all the way to westbound US 36 at Broomfield.
  • Take CO Highway 93 from Golden up to Boulder.

Site Surveys

Out of an abundance of caution, the survey team continues to periodically monitor the site. The damage continues to be isolated to one area. There continues to be no movement on the westbound side. It is stable and safe for traffic.

Crews will be working seven days a week to complete repairs safely and swiftly. Two travel lanes remain open in both directions.

The site is being monitored at all times to ensure continued safety for the traveling public.

Speed Up Your Commute

During the rebuild project on US 36, there will be increased congestion along the corridor. To alleviate congestion issues and reduce your commute time, there are alternatives to driving alone. Using the My Way to Go network, you can connect with carpools or vanpools along the US 36 corridor. Not only will this take cars off the road, it’s great for your wallet and the environment. Learn more about carpooling.

Vanpools are a great option for commuters who travel more than 15 miles to work one- way. Passengers share the ride in a vehicle — which, contrary to the name, isn’t always a van — that seats 5-15 people. Participants pay a monthly fee that covers the cost of fuel, insurance and vehicle maintenance. For a limited time, receive $20 a month off the cost of vanpooling through the VanCool program.

US 36 is also home to the Flatiron Flyer, RTD’s first Bus Rapid Transit (BRT) service to connect Boulder to Denver. The Flatiron Flyer offers commuters a reliable ride every 4 to 15 minutes during peak hours and every 15 minutes off-peak, Monday through Friday. 2019 Flatiron Flyer fares: $3 local three-hour pass and $5.25 regional three-hour pass. Click here to learn more about the Flatiron Flyer service.

Want to learn more? Commuting Solutions is the go-to resource for transportation solutions in the northwest metro region, spanning from Westminster to Longmont, that seeks to reduce traffic congestion, improve air quality and improve the lives of commuters in our region. Visit our website at commutingsolutions.org or email us at [email protected] for help finding your best commute.

CDOT and its contractor partner, Kraemer North America, have been hard at work rebuilding the eastbound US 36 wall. Geofoam installation continues, and approximately 3,500 geofoam blocks have been placed. More than 6,000 blocks of geofoam are expected to be used during this rebuild project. All geofoam is expected to be installed by the end of this week.

US 36 - 56 percent rebuild

What is Geofoam?

The rebuilt section of US 36 will include drilling concrete caissons down into the bedrock and placing a material called geofoam behind the retaining wall in place of the existing backfill. Geofoam is a lightweight backfill that has been used effectively in similar situations with settlement. Since geofoam is lightweight, it reduces pressure and stress to the underlying soil. It is also very strong, which means it can safely support highway loading and also lead to improved slope stability. Of the different options considered, this option provides the best factor of safety. The geofoam is being produced by Insulfoam, which has a local plant in Aurora.

Construction Timeframe

The No. 1 priority for CDOT and Kraemer North America has been to return eastbound US 36 to its original traffic pattern with three lanes in each direction. This is expected in October. In addition to opening traffic to the original alignment, crews will install a temporary bike path that will open to the public in October. Additional work on the wall, final bike path, and fence is expected to last through December.

Crews have been working every day to repair the damaged wall. All the geofoam has been delivered to the site, and the project team will work around-the-clock, both daytime and nighttime shifts, to restore the road to its original configuration.

Alternate Routes Available

Thank you for driving safely and being patient through the work zone. For estimated commute time, visit COtrip.org. Or, consider an alternate route:

  • Take I-25 north to 120th Avenue (CO 128 and US 287) and take that west to get back on westbound US 36 at Broomfield.
  • Similarly, you could take Federal Boulevard (US 287) north to 120th Avenue and take that same route to get back to US 36 westbound.
  • Take Wadsworth (CO 121) north all the way to westbound US 36 at Broomfield.
  • Take CO Highway 93 from Golden up to Boulder.

Site Surveys

Out of an abundance of caution, the survey team continues to periodically monitor the site. The damage continues to be isolated to one area. There continues to be no movement on the westbound side. It is stable and safe for traffic.

Crews will be working seven days a week to complete repairs safely and swiftly. Two travel lanes remain open in each direction on the westbound side during daytime hours.

The site is being monitored at all times to ensure continued safety for the traveling public.

Speed Up Your Commute

During the rebuild project on US 36, there will be increased congestion along the corridor. To alleviate congestion issues and reduce your commute time, there are alternatives to driving alone. Using the My Way to Go network, you can connect with carpools or vanpools along the US 36 corridor. Not only will this take cars off the road, it’s great for your wallet and the environment. Learn more about carpooling.

Vanpools are a great option for commuters who travel more than 15 miles to work one- way. Passengers share the ride in a vehicle — which, contrary to the name, isn’t always a van — that seats 5-15 people. Participants pay a monthly fee that covers the cost of fuel, insurance and vehicle maintenance. For a limited time, receive $20 a month off the cost of vanpooling through the VanCool program.

US 36 is also home to the Flatiron Flyer, RTD’s first Bus Rapid Transit (BRT) service to connect Boulder to Denver. The Flatiron Flyer offers commuters a reliable ride every 4 to 15 minutes during peak hours and every 15 minutes off-peak, Monday through Friday. 2019 Flatiron Flyer fares: $3 local three-hour pass and $5.25 regional three-hour pass. Click here to learn more about the Flatiron Flyer service.

Want to learn more? Commuting Solutions is the go-to resource for transportation solutions in the northwest metro region, spanning from Westminster to Longmont, that seeks to reduce traffic congestion, improve air quality and improve the lives of commuters in our region. Visit our website at commutingsolutions.org or email us at [email protected] for help finding your best commute.

CDOT and its contractor partner, Kraemer North America, have been hard at work rebuilding the eastbound US 36 wall. Geofoam installation began last week, and approximately 2,500 geofoam blocks have been placed. More than 6,000 blocks of geofoam are expected to be used during this rebuild project.

US36-RebuildGraphic

What is Geofoam?

The rebuilt section of US 36 will include drilling concrete caissons down into the bedrock and placing a material called geofoam behind the retaining wall in place of the existing backfill. Geofoam is a lightweight backfill that has been used effectively in similar situations with settlement. Since geofoam is lightweight, it reduces pressure and stress to the underlying soil. It is also very strong, which means it can safely support highway loading and also lead to improved slope stability. Of the different options considered, this option provides the best factor of safety. The geofoam is being produced by Insulfoam, which has a local plant in Aurora.

Construction Timeframe

The No. 1 priority for CDOT and Kraemer North America has been to return eastbound US 36 to its original traffic pattern with three lanes in each direction. This is expected in October. Additional work on the wall, final bike path, and fence is expected to last through December.

Crews have been working every day to repair the damaged wall. After Labor Day, all the geofoam will have been delivered to the site, and the project will return to working daytime and nighttime shifts to restore the road to its original configuration.

Alternate Routes Available

Thank you for driving safely and being patient through the work zone. For estimated commute time, visit COtrip.org. Or, consider an alternate route:

  • Colorado Highway 128 (120th Avenue)
  • Colorado Highway 7
  • Colorado Highway 93 from Golden to Boulder
  • Northwest Parkway (please note, this route is tolled)

Site Surveys

Out of an abundance of caution, the survey team continues to periodically monitor the site. The damage continues to be isolated to one area. There continues to be no movement on the westbound side. It is stable and safe for traffic.

Crews will be working seven days a week to complete repairs safely and swiftly. Two travel lanes remain open in each direction on the westbound side during daytime hours.

The site is being monitored at all times to ensure continued safety for the traveling public.

Speed Up Your Commute

During the rebuild project on US 36, there will be increased congestion along the corridor. To alleviate congestion issues and reduce your commute time, there are alternatives to driving alone. Using the My Way to Go network, you can connect with carpools or vanpools along the US 36 corridor. Not only will this take cars off the road, it’s great for your wallet and the environment. Learn more about carpooling.

Vanpools are a great option for commuters who travel more than 15 miles to work one- way. Passengers share the ride in a vehicle — which, contrary to the name, isn’t always a van — that seats 5-15 people. Participants pay a monthly fee that covers the cost of fuel, insurance and vehicle maintenance. For a limited time, receive $20 a month off the cost of vanpooling through the VanCool program.

US 36 is also home to the Flatiron Flyer, RTD’s first Bus Rapid Transit (BRT) service to connect Boulder to Denver. The Flatiron Flyer offers commuters a reliable ride every 4 to 15 minutes during peak hours and every 15 minutes off-peak, Monday through Friday. 2019 Flatiron Flyer fares: $3 local three-hour pass and $5.25 regional three-hour pass. Click here to learn more about the Flatiron Flyer service.

Want to learn more? Commuting Solutions is the go-to resource for transportation solutions in the northwest metro region, spanning from Westminster to Longmont, that seeks to reduce traffic congestion, improve air quality and improve the lives of commuters in our region. Visit our website at commutingsolutions.org or email us at [email protected] for help finding your best commute.

CDOT and its contractor partner, Kraemer North America, have been hard at work since the middle of last week rebuilding the eastbound US 36 wall. Over the weekend, crews completed the rock foundation underneath the wall. Now, geofoam installation is underway. More than 6,000 blocks of geofoam are expected to be used during this rebuild project.

Eastbound US 36 Geofoam

What is Geofoam?

The rebuilt section of US 36 will include drilling concrete caissons down into the bedrock and placing a material called geofoam behind the retaining wall in place of the existing backfill. Geofoam is a lightweight backfill that has been used effectively in similar situations with settlement. Since geofoam is lightweight, it reduces pressure and stress to the underlying soil. It is also very strong, which means it can safely support highway loading and also lead to improved slope stability. Of the different options considered, this option provides the best factor of safety. The geofoam is being produced by Insulfoam, which has a local plant in Aurora.

Construction Timeframe

The No. 1 priority for CDOT and Kraemer North America has been to return eastbound US 36 to its original traffic pattern with three lanes in each direction. This – along with a temporary bike path - is expected in October. Additional work on the wall, final bike path, and fence is expected to last through December.

Alternate Routes Available

Thank you for driving safely and being patient through the work zone. For estimated commute time, visit COtrip.org. Or, consider an alternate route:

  • Colorado Highway 128 (120th Avenue)
  • Colorado Highway 7
  • Colorado Highway 93 from Golden to Boulder
  • Northwest Parkway (please note, this route is tolled)

Site Surveys

Out of an abundance of caution, the survey team continues to periodically monitor the site. The damage continues to be isolated to one area. There continues to be no movement on the westbound side. It is stable and safe for traffic.

Crews will be working seven days a week to complete repairs safely and swiftly. Two travel lanes remain open in each direction on the westbound side during daytime hours.

The site is being monitored at all times to ensure continued safety for the traveling public.

Over the past weekend, CDOT and its contractor partner, Kraemer North America, made significant progress in the removal of portions of the eastbound US 36 wall. Crews finished removing the wall today and will begin rebuilding the wall immediately. Today, Wednesday, Aug. 14, crews will install a 24-inch storm sewer pipe and backfill this area to construct a strong foundation for the rebuild.

US 36 100 Removal

Geofoam Deliveries

The rebuilt section of US 36 will include drilling caissons down into the bedrock and placing a material called geofoam behind the retaining wall in place of the existing backfill. Geofoam is a lightweight backfill that has been used effectively in similar situations with settlement. Since geofoam is lightweight, it reduces pressure and stress to the underlying soil. It is also very strong, which means it can safely support highway loading and also lead to improved slope stability. Of the different options considered, this option provides the best factor of safety. The geofoam is being produced by Insulfoam, which has a local plant in Aurora.

Trucks have actively been delivering geofoam blocks since last week. Work to install the geofoam is estimated to begin Monday, Aug. 19.

To date, 1,226 blocks of geofoam have been delivered. An estimated 6,700 blocks of geofoam are expected to be used during the rebuild of US 36.

Site surveys are ongoing

Out of an abundance of caution, the survey team continues to monitor the damaged section of roadway. The damage is isolated to one area, and surveys have shown that the damaged section has settled. There continues to be no movement on the westbound side. It is stable and safe for traffic.

Crews will be working seven days a week to complete repairs safely and swiftly. Some overnight lane closures are anticipated, but impacts to traffic are expected to be minimal during reconstruction. Two travel lanes remain open in each direction on the westbound side during daytime hours.

The site is being monitored at all times to ensure continued safety for the traveling public.

Stay in Touch with the Project

During this construction, safety is of utmost importance.

US36-RemovalGraphic_vFINAL.jpg

Over the past weekend, CDOT and its contractor partner, Kraemer North America, made significant progress in the removal of portions of the eastbound US 36 wall. Working from top to bottom, the team has removed 75% of the wall. Crews will continue removal throughout the rest of this week and weekend.

Once the wall is safely removed, crews will then begin to remove four feet of dirt below the wall and replace it with better material. Then, crews will start to rebuild the wall.

Overnight single lane closures tonight, Tuesday and Wednesday

Drivers who travel US 36 between Westminster and Boulder can expect delays overnight Monday, Aug. 5, Tuesday, Aug. 6, and Wednesday, Aug. 7, as crews install glare screen on the temporary concrete barrier used to shift traffic for the Eastbound US 36 Emergency Rebuild Project.

To enhance safety for the traveling public in this construction zone, crews will now install green slats, called glare screen, on top of the concrete barrier used to separate traffic. This will help to reduce headlight glare and increase nighttime visibility for drivers along the corridor.

To safely complete this work, crews will close the left lanes of both eastbound and westbound US 36 in the half-mile construction zone between Wadsworth Boulevard and 104th Avenue. The lane closures are expected from 10 p.m. to 5 a.m. Monday, Aug. 5, Tuesday, Aug. 6, and Wednesday, Aug. 7. Drivers will still have one lane for travel but should expect minor delays.

Site surveys are ongoing

Out of an abundance of caution, the survey team continues to monitor the damaged section of roadway. The damage is isolated to one area, and surveys have shown that the damaged section has settled. There continues to be no movement on the westbound side. It is stable and safe for traffic.

Crews will be working seven days a week to complete repairs safely and swiftly. Some overnight lane closures are anticipated, but impacts to traffic are expected to be minimal during reconstruction. Two travel lanes remain open in each direction on the westbound side during daytime hours.

The site is being monitored at all times to ensure continued safety for the traveling public.

During this construction, safety is of utmost importance.