Drew Dix Parkway Dillon Drive at I-25 Interchange
About the Project:
This safety and mobility improvement project will construct a roundabout at the intersection of Drew Dix Parkway and the west frontage road. The southbound I-25 off-ramp at Drew Dix Parkway (exit 104) will be realigned to utilize the new roundabout.
The east frontage road will be built between Drew Dix Drive and Dillon Parkway. This new connection will run parallel to northbound I-25 between the existing roundabout at Dillon Drive and the Drew Dix Parkway / northbound I-25 on-ramp intersection.
Project Benefits:
- Better circulation between Drew Dix Parkway, Dillon Drive and I-25
- Roundabout intersection design improves safety
- Completion of ultimate design concept partially constructed in 2016 as part of the Dillon Drive Interchange Project
Major work items:
- New roundabout at Drew Dix Parkway, west frontage road, southbound I-25 off-ramp intersection
- Frontage road construction east of I-25 between Dillon Drive and Drew Dix Parkway including a new bridge
- Drainage improvements including a new concrete box culvert
- New sidewalk connections
- Lighting improvements
- Signing and striping
- Guardrail installation
Work Schedule:
- Anticipated work hours will be from 7 a.m. to 7 p.m. Monday through Friday.
- Infrequent night and weekend work may be necessary for some construction activities.
Traffic Impacts:
- Expect activity occurring off the roadway and adjacent to the Drew Dix Parkway / west frontage road intersection.
- Through traffic on I-25 will not typically be impacted by construction since work is occurring away from the interstate.
- Access to all properties will be maintained during construction.
- Expect frequent traffic pattern changes.
-
Work this Week & Lane Closures
Drew Dix Parkway Dillon Drive at I-25 Interchange
Project Facts
- Cost: $10 Million
- Contractor: SEMA
- Timeline: March 2023 - Fall 2024
- Location: Drew Dix Parkway/Dillon Drive at I-25, Pueblo County