CO 97 Nucla Sidewalk Reconstruction
About the Project
The project consists of revitalizing the sidewalks on Main Street in Nucla. The sidewalk improvements will take place on:
- West side of CO Highway 97 (Main Street) from 3rd Avenue to 5th Avenue
- East side of CO 97 from 4th Avenue to 5th Avenue
Crews will begin work on the west side of CO 97 by deconstructing the original concrete then replacing the sidewalk concrete with ADA ramps and bump outs. Once work is complete from 3rd Avenue to 4th Avenue, crews will move to the east side of 4th Avenue to 5th Avenue
Construction is expected to be completed by July 2025, weather permitting.
Project Facts
- Construction Cost: To be announced
- Contractor: Williams Construction
- Timeline: March 2025 to June 2025
- Location: CO 97 (Main Street)
- Nearest Town/City: Nucla
- Mile Point(s): MP 4.34 to MP 4.53
- County: Montrose
Work Schedule
- Work hours will range from 7 a.m. to 7 p.m., Monday through Friday
- March 31, 2025 to April 4, 2025:
- 3rd Ave to 4th Ave (west side) - Concrete pouring
- Starting April 3, from 4th to 5th Ave (west side) - Sidewalk demo work / Sidewalk concrete prep work
- April 7, 2025 to April 11, 2025:
- 4th to 5th Ave (west side) - Sidewalk demo work / Sidewalk concrete prep work
- 4th to 5th Ave (west side) - Begin pouring curb and gutter
- April 14, 2025 to April 18, 2025:
- 4th to 5th Ave (west side) - Sidewalk concrete pouring
- All scheduling is subject to change due weather or unforeseen circumstances
Traffic Impacts
Businesses and motorists can expect temporary impacts as crews work along Main Street:
- Shoulder closures on Main Street from 3rd Avenue to 5th Avenue (MP 4.34 to MP 4.53)
- The intersection at 4th Avenue and Main Street will be temporarily closed from March 24 through March 28
- Slow down when approaching the work zone, drive with caution, allow extra space between vehicles and give extra travel time
- Visit COtrip.org for the most current project work zone locations and road closures