CO 82 Twin Lakes Resurfacing
About the Project
The project will improve approximately seven miles of CO 82 from one mile west of Twin Lakes (Mile Point 78) to CO 82/US 24 intersection (MP 85.3).
Work will include:
- Milling old asphalt
- Paving with new asphalt
- Guardrail replacement
- Bridge rehabilitation
Bridge rehabilitation will take place at MP 84.3 and will consist of bridge rail replacement and bridge deck repairs.
Work this Week & Lane Closures on CO 82 Twin Lakes
Project Facts
- Construction Cost: $4.9 million
- Contractor: Elam Construction
- Timeline: Mid-April 2025 through September 2025
- Location: CO 82
- Nearest Towns/Cities: Aspen, Leadville
- Mile Point(s): MP 78 to MP 85.3
- County: Lake

Project Benefits
The new asphalt will provide the following benefits:
- Add years of life to the highway
- A smoother road surface
- Add durability by increasing the resistance of ruts and road damage
Other benefits of the project include:
- Installation of new guardrail that will be 31 inches high, designed to meet new safety standard requirements
- Higher railing will help veering vehicles remain on the road more effectively, making the highway safer for the traveling public
- The former standard height of guardrail was 27 inches.
Work Schedule
- Daytime work hours are Monday through Thursday from 7 a.m. to 7 p.m. and Friday from 7 a.m. to noon
Traffic Impacts
Motorists can expect the following impacts during the period of construction:
- 20-minute delays
- A speed reduction to 40 MPH
- One-lane alternating traffic guided by flagging personnel
- 10-foot width restriction
- Refer to COtrip.org for real-time travel conditions and road closures