CO 71 Widening between Rocky Ford & Ordway

About the Project

Work will occur along Colorado Highway 71, north of County Road HH 5 and south of Bob Creek, Mile Point 18.75 to MP 20.75. 

Work will primarily consist of:

  • Installing a passing lane
  • Sign and delineator installation
  • New fence installation
  • Pavement markings

Work will be done in the northbound and southbound lanes for a two-mile stretch of CO 71.

Work this Week & Lane Closures on CO 71 between Rocky Ford & Ordway

Project Facts

  • Construction Cost: $2.3 Million
  • Contractor: Pyramid Construction, Inc.
  • Timeline: Mid-February 2025 to end of July 2025
  • Location: CO 71 
    • Nearest Towns/Cities: Rocky Ford and Ordway
    • Mile Point(s): MP 18.75 to MP 20.75
    • Counties: Otero and Crowley
CO 71 Widening project location map from MP 18.75 to MP 20.75
CO 71 Widening project location map from MP 18.75 to MP 20.75 between Rocky Ford and Ordway

Work Schedule

  • Work will last approximately five and a half months
  • Daytime work hours:
    • Monday through Friday, range from 30 minutes after sunrise (approximately 7 a.m.) to 30 minutes before sunset (approximately 4:30 p.m.)  
    • Potentially some Saturday work

Traffic Impacts

  • Vehicles will be reduced to a single-lane, alternating traffic intermittently in either direction throughout the duration of the project
  • Lane closures, guided by flaggers and traffic control devices, will have up to 15-minute delays
  • The speed limit will be reduced to 45 mph through the work zone with flaggers and 50 mph without flaggers