CO 71 Overlay between Ordway and Punkin Center
About the Project:
Full depth reclamation on CO 71 between Ordway and Punkin Center. Hot mix, structure and culvert work
Benefits
- Resurfacing can significantly extend the life of the asphalt pavement
- A smoother surface offers safer driving
- A smooth road or highway improves the safety and quality of the driving experience
Work Schedule:
- Construction will begin on July 17th
- Daytime work hours are Monday through Friday ½ hour after sunrise
(approx. 6:30 a.m.) and end a half hour before sunset (approx. 8 p.m.). - The project is anticipated to end in late November of 2023
Traffic Impacts:
- Motorists should plan for 15-20 minute delays due to single-lane, alternating traffic
- The speed limit will be reduced to 40 MPH through the work zone
- There will be a width restriction of 12 feet
- Bridge work traffic will be an alternating single lane and controlled by traffic lights 24/7
- Refer to COtrip.org for real-time travel conditions and road closures
Work this Week & Lane Closures
CO 71 Overlay
Project Facts
- Construction Cost: $14.3 Million
- Contractor: A & S
- Timeline: mid July through November 2023
- Location: CO 71
- Nearest Town/City: between Ordway and Punkin Center
- Mile Point(s): 48.66 to 63.80
- County: Lincoln