The Colorado Department of Transportation is improving pedestrian walkways with the installation of American Disabilities Act (ADA) complaint curb ramps at various locations along SH 14, US 287 and the Prospect Rest Area off I-25 in the Fort Collins area.

Curb ramps are intended to provide pedestrians access between the sidewalk and street with ease when a vertical change in elevation is present. For those with disabilities, curb edges can be hazardous and requirements are put in place to help prevent dangerous situations such as people falling out of wheelchairs, or while using a cane or walker.


Work Schedule

  • Work throughout this corridor is scheduled to begin August 15, 2021 and last through September
  • Daytime lane closures will be Monday through Friday, from 8 a.m. to 5 p.m.

Traffic Impacts

Anyone traveling this corridor can expect throughout the project:

  • Construction work Monday through Friday, during the hours of 8 a.m. to 5 p.m.
  • Occasional single right lane closures
  • Sidewalk closures at some locations for pedestrians

Project Facts

  • Cost: $376,000
  • Contractor: Colorado Civil Infrastructure
  • Timeline: August - September 2021
  • Location: CO 14, US 287 and Prospect Rest Area off I-25 in Fort Collins