CO 14 & CO 125 Resurfacing in Walden

Work this Week
September 26 - October 1, 2022

Crews are in the final phases of completing this project, and anticipate work to be wrapped up by the end of this week.  

  • Working hours on CO 14 and CO 125 will be from 7 a.m. to 6 p.m., Monday through Friday. There will be possible intermittent single lane and shoulder closures in sections of both project locations. These are not anticipated to cause significant delays.
  • Motorists should slow down as they approach the work zones, drive with caution, allow extra space between vehicles and give themselves extra travel time.

Paving nearing completion in downtown Walden"

Paving nearing completion in- downtown Walden"

About the Project:

The project will consist roadway resurfacing using a mill and overlay process along CO 14 and CO 125 in Walden. Additionally, two locations along CO 14 will be widened for truck turnarounds. The first phase of the project will begin at the end of May along an 8 mile stretch of CO 14, from Mile Point 11.0 to 19.0. Starting in mid-July, crews will move operations to CO 125 through downtown Walden from MP 52.3 to 55.0. The project will improve and prolong the life of the road surface, offering a safer and smoother travel path for all motorists. Work is expected to go from the end of May to mid-August.


Work Schedule

  • Daytime working hours will range from 7:00 a.m. to 6:00 p.m., Monday through Friday.

Traffic Impacts

  • Vehicles may be reduced to a single-lane, alternating traffic intermittently in either direction throughout the duration of the project.
  • The speed limit will be reduced to 40 mph on CO 14 through the work zone.
  • Lane closures are not expected to significantly impact traffic flow, but may cause minimal delays. Please plan accordingly when determining your travel times.
  • For real-time lane closure information for this project and others across the state please visit cotrip.org.

Project Facts

  • Cost: $5.4 Million
  • Contractor:  McAtee Construction Co.
  • Timeline: May - August 2022
  • Location: CO 125 through the town of Walden from MP 52.3 to 55.0, and 8 miles of CO 14 from MP 11.0 to 19.0 in Jackson County.