CO 115 Resurfacing in Colorado Springs
About the Project
Work will occur along Colorado Highway 115 from Fort Carson north to Colorado Springs from Mile Point 41.5 to MP 47.3. Work will be done in both the northbound and southbound lanes for a six-mile stretch of CO 115.
Work will primarily consist of:
- Resurfacing the roadway
- Replacing curb ramps and guardrails
- Updating pedestrian signals
Project Benefits
- The project will improve and prolong the life of the road surface
- A smooth road or highway has many important benefits, including safety and improved quality for the driving experience
- A smoother surface also offers safer driving for motorists
Work Schedule
- Working hours will vary depending on the nature of the work, direction of travel, and type of traffic control needed
- Major work items, such as paving, will occur during nighttime hours, and other work items may occur during daytime work hours
- Northbound: Sunday through Thursday, from 8 p.m. to 7 a.m.
- Southbound: Sunday through Thursday, from 7 p.m. to 7 a.m.
Traffic Impacts
- Refer to COtrip.org for real-time travel conditions and road closures
Work this Week & Lane Closures on CO 115 from Fort Carson to Colorado Springs
Project Facts
- Construction Cost: $10.4 Million
- Contractor: Schmidt Construction Company
- Timeline: February 2025 to September 2025
- Location: CO 115
- Nearest Towns/Cities: Fort Carson and Colorado Springs
- Mile Point(s): MP 41.5 to 47.3
- County: El Paso