CO 115 Improvements - Colorado Springs to Penrose

Work this Week
August 8 - 12, 2022

Anticipated traffic impacts for the week of 8/8/2022 include:

  • Daily shoulder closures, Monday through Friday (MP 35.5 to 39.0)
  • Single lane closures, Monday through Friday (MP 35.5 to 39.0) - some travel delay expected
  • Intermittent flagging, Monday through Friday (MP 35.5 to 39.0) - follow crew instructions
  • New traffic pattern - one lane in each direction from Roca Roja Circle (mile point 35.5) and Rock Creek Canyon Road (MP 39)
  • Reduced work zone speed limit of 45 mph
  • Oversize vehicle width restriction of 11 feet

Construction activities include:

  • Clearing and grading activity
  • Stockpiling material
  • Asphalt milling and removals

All work is weather-dependent and subject to change.

About the Project:

CDOT is constructing a major improvement project on Colorado Highway 115. The project improves roadway and bridge safety on CO 115 from mile point (MP) 27.7 to MP 39 by adding passing lanes, right turn lanes, reconstructing Rock Creek Bridge, and performing major rehabilitation or reconstruction of cracked and distressed pavement


Work Schedule:

  • Phased construction from July 2022 - December 2023
  • Crews will primarily work during daylight hours Monday through Friday.
  • Night and weekend work are anticipated for several work activities to expedite construction and reduce traffic impacts.

Traffic Impacts:

  • -Initial construction activities require shoulder closures between Roca Roja Circle (mile point 35.5) to Rock Creek Canyon Road (MP 39).
  • Crews are preparing for a major traffic pattern change, which will reduce approximately three miles of CO 115 to one lane in each direction, in early August.
  • The initial phase of construction will focus on the northern three miles of the work zone (MP 35.5 – MP 39).

Project Facts

  • Cost: $40 Million
  • Contractor: Castle Rock Construction
  • Timeline: July 2022 - December 2023
  • Location:  CO 115 from Colorado Springs to Penrose, El Paso County

CO 115 Improvements project map