CO 52 & Weld County Road 37 Intersection Improvements

Work this Week
November 28 - December 3, 2022

Anticipated traffic impacts for the week of 11/28/2022 include:

  • CR 37 is OPEN and all turning movements are possible at the intersection

  • CO 52 and CR 37 intermittent lane closures (Monday through Friday) from 7 a.m. to 5 p.m. for equipment access and finishing work

  • Intermittent flagging, follow crew instructions

Anticipated construction activities include:

  • Finishing work

All work is weather-dependent and subject to change.

About the Project:

The Colorado Department of Transportation and AB Underground will construct safety improvements at the intersection of Colorado Highway 52 and Weld County Road 37. This project will add left-turn lanes on all intersection approaches in addition to a right-turn lane from eastbound CO 52 to southbound WCR 37. New culverts and roadside ditches are part of the project. The work zone will be resurfaced with asphalt, and signing and striping upgrades will enhance safety and visibility.

Project map


Work Schedule:

  • General work hours are from 7 a.m. to 5 p.m., Monday through Friday with occasional extended hours and weekend work
  • Project completion is anticipated in December 2022
  • Construction schedules are weather dependent and subject to change

Traffic Impacts:

  • Expect frequent traffic shifts and lane closures with flagger control
  • Adjacent property access will be maintained

Project Facts

  • Cost: $3.1 Million
  • Contractor: AB Underground
  • Timeline: August - December 2022
  • Location: Intersection of CO 52 and WCR 37 between Fort Lupton and Hudson

CO 52 & CR 37 location map