Projects

CO 119 Boulder Canyon Improvements

Paving complete on CO 119 in Boulder Canyon 

Project nears completion, but not yet at the finish line

Crews on the Colorado Highway 119 project have reached a significant milestone by completing all paving between Boulder and Nederland. After reconstructing several portions of the highway and completing the paving, the temporary traffic signals have been removed and cycling restrictions lifted. Work continues on the pedestrian path, but cyclists can now travel the corridor in both directions on the roadway.

Completing paving was prioritized as seasonal temperatures have been dropping, and although the project is nearing the finish line, a handful of key items are ongoing. Daily single-lane closures will be used through January for retaining wall construction, guardrail installation and work related to extending the trail. Following this work, crews will return in spring 2021 for temperature-dependent work such as striping, landscape, and sign and delineator installation.

“Our crews have been working meticulously to complete the paving work before winter and we are very proud to have reached this milestone,” CDOT Regional Transportation Director Heather Paddock said. “We are grateful to the surrounding communities for their patience during this impactful work.”

Overall, the project has made significant progress this year. In addition to completing the paving work, crews also completed 66,000 cubic yards of rock excavation and placed 58,000 tons of asphalt. The Nederland Roundabout construction, rock scaling, construction of the pedestrian tunnel, and the Boulder Falls parking lot reconstruction are also complete.

The team will continue to coordinate project impacts with emergency responders.

There’s no denying that our daily lives have changed drastically in the last two weeks, and in some cases, lives have been turned upside down. Small town tourism industries, in particular, has been hard hit, and that doesn’t go without notice to the construction crews working in Boulder Canyon. Many sacrifices are being made from closing businesses and schooling children at home to canceling events and moving work operations to our homes where possible.

While telecommuting might work for some occupations, construction clearly isn’t one of those. Without people physically on site to do the work, the CO 119 Boulder Canyon project would continue to be delayed and never become a reality. But while road work is progressing for now, that’s not to say it is totally business as usual on the jobsite. As you know, safety is always a top priority for CDOT, and that includes safety precautions during this virus pandemic. Here are some of the things work crews are doing a little differently these days:
  • Crew members are refraining from going into jobsite trailers or project offices unless absolutely necessary, and when they have to, they aren’t doing so in groups.
  • Daily safety briefings are being done with just a couple of people rather than the entire crew.
  • Paperwork is being done in the cab of pickup trucks and daily logs of work activities filled out at home.
  • Project management meetings have been scaled back where possible, and any meetings involving more than a few people are being conducted via phone.
  • Everyone is being told to NOT report to work if they feel ill, and anyone who doesn’t feel well on the job is immediately sent home.
  • All office staff and non-essential personnel who can work from home are doing so.
  • Though all workers in the field wear gloves, hand tools are being cleaned more vigilantly and workers are instructed to wash or sanitize their hands after removing gloves.
  • Workers are bringing their own water bottle to the jobsite to avoid using a common water cooler.
  • Portable restrooms are being sanitized more frequently.
  • Steering wheels and machinery equipment controls are being wiped down, particularly if different people will be moving in and out of the equipment throughout the day.
  • Crews are communicating via radio instead of face-to-face.
  • Flaggers are staying at least 6 feet away from stopped cars and will not be accepting any gifts from drivers. As drivers, please refrain from rolling down your windows and speaking with flaggers during this time.

Sunday, November 29 - Saturday, December 5

  • Flagged single-lane closures will be used between Nederland and Boulder from 7 a.m. - 7 p.m. Monday through Friday. No temporary traffic signals are currently in use.
  • Colorado Highway 119 - Boulder Canyon will have single-lane closures. During working hours, there will be up to four areas impacted concurrently.
  • Up to 40-minute delays are expected through the canyon during work hours. Speed limits are reduced to 25 miles per hour in the construction zones. The work is weather-dependent, and the schedule may change.
  • No work will occur Thursday, Nov. 26 – Sunday, Nov. 29. Please drive safely and have a Happy Thanksgiving. 

24/7 Ongoing Impacts

  • Road reconstruction and bridge repair is underway between MP 39 and 40. Concrete flatwork also continues in Nederland.
  • Flagged single-lane closures will be used between Nederland and Boulder from 7 a.m. to 7 p.m. Monday through Friday. No temporary traffic signals are currently in use.
  • Motorists will be guided around the single-lane closures with traffic control flaggers.
  • Please continue to plan additional time to travel through the construction zones.

Trail Closures and Cycling Updates

  • The FULL CLOSURE of the Boulder Canyon trail at MP 40 where it crosses under Colorado Highway 119 will remain in place throughout 2020, preventing through access from Boulder to the Four Mile trailhead.
  • Cycling access is now open through the canyon. Cyclists need to follow the last car through single-lane closure areas.
  • The Boulder Falls parking lot (near MP 33) is now open.

Creek Closure

  • The Boulder Canyon Creek will be closed to all uses between Canyon Park Drive (Boulder) and Boulder Falls until further notice.



Project Facts

  • Cost: $31 Million
  • Contractor: Zak Dirt
  • Timeline: Winter 2019 - December 2020
  • Location: CO 119 between Boulder and Nederland
  • Alternate Route During Construction: CO 72 is a recommended detour. Learn more about the CO 72 Coal Creek Canyon project.

About the Project

In March 2019, crews began repairing a 15-mile stretch of Colorado Highway 119, between Boulder and Nederland, which was damaged during flooding in 2013.

Work includes:

  • resurfacing 13 miles of highway, and entirely replacing two miles of highway;
  • building concrete islands to improve the roundabout in Nederland;
  • installing new highway directional and safety signage;
  • replacing multiple pipes conveying stormwater drainage under the highway;
  • scaling rock in selected areas to reduce rockfalls on the highway;
  • repairing soft shoulder areas immediately adjacent the highway;
  • replacing 29,000 linear feet of concrete or metal guardrail;
  • removing and replacing materials placed during emergency repairs;
  • excavating areas where the slope had failed in the storm;
  • redesigning and widening specific sections of the roadway;
  • reconstructing embankments; and
  • re-establishing native grass seed and erosion control to slopes that were disturbed during emergency recovery work.

Boulder County Trail Improvements

The project, in partnership with Boulder County, will extend and reinforce sections of the Boulder Canyon Trail. The 10-foot-wide, multi-use trail will be extended from Four Mile Canyon to Chapman Drive—adding two new bike-friendly tunnels under the highway and approximately 3500 feet of length to the trail.


Project Work Hours:

  • 7 a.m. - 7 p.m., Monday - Friday
  • No night or weekend work is planned. However, some work zones will remain closed to preserve the work area.

Travel Impacts & Delays

Local detours remain available. From Boulder, a northern alternate route can be taken via CO 7, US 36 and CO 72. A southern alternate route is available via CO 93 and CO 72. Please note, motorists taking the southern alternate route should be aware of a current project on CO 72 in Coal Creek Canyon, between Plainview Road (mile point 12.3) and Pinecliffe (MP 24.6). Expect lane shifts and short delays at this work zone. 

Various delays from single lane & full road closures are expected throughout the project.  Motorist are strongly encouraging everyone to plan ahead to give yourselves enough time to reach your destination.

  • Expect various long-term single-lane closures managed by temporary traffic signals, and various short-term single-lane closures managed by flagging.
  • Plan for 40-Minute Delays.
  • Speed limits will be reduced to 25 mph in the work zones. Expect several stops through the corridor.  
  • A permit-load restriction will be in effect.


Do Not Drive Distracted

CDOT does not encourage drivers to make calls or use any apps while driving. Distracted driving is the act of driving while engaged in anything—texting, looking after children or pets, talking on the phone or to a passenger, watching videos, eating, or reading—that takes a driver's focus away from the road. Distracted drivers cause an average 43 crashes each day in Colorado. In 2018, there were 15,673 crashes in Colorado that involved a distracted driver.

Finally, CDOT used 100% solar to power the WiFi system. This system will function throughout the night and several days without sun. This wifi will only be available throughout the duration of the project.


Colorado: The Official State Web Portal