General Impacts, Schedule & Scope of Work
- The project began in May 2024 with a duration of up to 18 months
- The project entered a winter hiatus on Dec. 21, 2024 and returned on Feb. 18, 2025
- Work includes adding a single lane roundabout with bypass lanes at the Quincy and C-470 northbound ramp intersection, and a T-intersection with traffic signal at the Quincy and C-470 southbound ramp intersection
- Other work includes adding capacity, building retaining walls, installing signs, and making drainage improvements
- Periodic on and off ramp closures to and from C-470 at Quincy Ave will be taken during off-peak daytime as well as overnight hours
- Some closures of half the existing Quincy Ave over C-470 bridge will be taken for roundabout and other construction, with two-way traffic maintained and 12-ft width restriction in place
- A single lane closure on northbound C-470 will exist later in the project for sign work
- No work will take place on mainline C-470
- Normal working hours will be from 7 a.m. to 6 p.m. Monday to Friday
- The project limits on C-470 extend from MP 6.10 to MP 6.80
- The project limits on Quincy extend from MP 0 to MP .56
- Signs and construction devices will be present to alert the public to the work zone, closures and restrictions
- Construction schedules are weather dependent and subject to change
- Please refer to COtrip.org for real-time travel conditions and to plan your trips!
|
|