CO 330 Resurfacing to Collbran

Project Complete

About the Project

Work will consist of resurfacing the roadway by applying a 1.5 inch inch full-width hot asphalt overlay to the existing road surface, adding additional gravel to the shoulders, repairing and replacing guardrail, and restriping the roadway surface with six inches center and edge lines. Work will be done in both the eastbound and westbound lanes for the entire length of CO 330 from the intersection with CO 65 to the Town of Collbran, an 11.4-mile stretch.

Project Facts

  • Cost: $3 million
  • Contractor: United Companies
  • Timeline: July 2020 to October 2020
  • Location: CO 330 from intersection with CO 65 to the Town of Collbran


Proposed Work Schedule

  • Daytime work hours range from 7 a.m. to 7 p.m. Monday through Friday


Traffic Impacts

  • Vehicles may be restricted to single-lane, alternating traffic intermittently in either direction, throughout the duration of the project. These lane closures, guided by flaggers and pilot cars, may have up to 15-minute delays.
  • During installation of the box culvert at MP 2.58, a temporary traffic signal will be in place 24/7 to guide traffic through the single open lane, with potential 5-minute delays. 
  • The speed limit will be reduced to 25 mph through the work zone. Traffic fines in the construction zone will be doubled. The project is expected to last until mid-October.  
  • Loads wider than 12 feet will be restricted 7 a.m. to 7 p.m. during paving operations and 24/7 during culvert replacement (dates to be determined).  Questions about load restrictions and delays can be directed to the project team using the contact information below.