CO 119 Wall Repair in Black Hawk
Project Complete
About the Project
In early February, Hamilton Construction will begin work on CO Highway 119 west of the intersection with Mill Street (mile point 6.8). Benefits: This work is necessary to improve the safety of the highway by strengthening and repairing the retaining wall supporting the embankment upstream from the intersection of Mill Street and CO 119.
Work Includes:
- minor excavation and backfill
- installation of a temporary platform on the creek side
- removal and replacement of portions of the guardrail
Project Facts
- Cost: $481,505
- Contractor: Hamilton Construction
- Timeline: January - April 2020
- Location: On CO 119 at Mill Street in Black Hawk
Benefits
This work is necessary to improve the safety of the highway by strengthening and repairing the retaining wall supporting the embankment upstream from the intersection of Mill Street and CO 119.