Walsenburg Pedestrian/Bicycle Improvements

Project Completed

Project Facts

  • Cost: $1.7 million
  • Contractor: Walsenburg Sand and Gravel
  • Timeline: May 2019 to December 2019
  • Locations: I-25 C (Walsen Avenue) between Spruce and Pine; and on US 160 between Olive and Ysidro in Walsenburg

In December 2019, crews completed the upgrade of curb ramps and sidewalks on I-25C and on US 160 in Walsenburg to ensure they complied with the Americans With Disabilities Act (ADA).

Other work included:

  • installing permanent traffic-control devices;
  • improving pedestrian crossings; and
  • modifying a culvert to accommodate a multi-use shared path on Walsen and Pine.

Crews completed work at the following locations:

  1. Interstate 25C (Walsen Avenue), between Spruce Street (MP 1.9) and Pine Street (MP 2.3)
  2. US 160 (Seventh Avenue) between Olive Street (MP 304.72) and Ysidro Street (MP 304.85).

Schedule

  • No further traffic impacts

Traffic Impacts

  • No further traffic impacts