US 6 Brush Creek Bridge

Project completed

About the Project

In late 2015, CDOT completed this project, which replaced the bridge at US 6, mile point (MP) 148.35, over Brush Creek, near the town of Eagle. The project also improved drainage in Hockett Gulch by replacing the old system with a larger, improved culvert.

The project ran from MP 148-149 on US 6 and included grading, with larger embankments, paving and striping.

The contractor on this $3.8 million project was Ralph L Wadsworth of Draper, Utah.