US 50 Cañon City Road Maintenance
Project completed
About the Project
This project is located in Southeastern Colorado (Region 2) in Fremont County. Project work consists of preventative maintenance micro surfacing treatment on US50A.
Project Benefits
- Microsurfacing is a protective seal coat that extends the life of the pavement.
- This is a cost-effective method to renew the road surface and seal minor cracks and other irregularities.
- A smoother surface offers safer driving
Work Schedule:
- Construction will begin on June 5th
- Sunday through Friday from 7 p.m. to 7 a.m.
- The project is anticipated to end in late July of 2023
Traffic Impacts:
Motorists can expect the following impacts during the period of construction:
- Intermittent single-lane, alternating traffic through the work zone throughout the duration of the project
- Both directions of traffic will be affected
- Vehicles will be reduced to an 11-foot lane width restriction
- Delays of up to 15 minutes are anticipated
- Motorists are to follow directions from flaggers on site.
- Refer to COtrip.org for real-time travel conditions and road closures
Project Facts
- Construction Cost: $2 Million
- Contractor: Geneva Rock
- Timeline: June through July 2023
- Location: US 50
- Nearest Town/City: Cañon City
- Mile Point(s): 278 to 282
- County: Fremont