US 385 Resurfacing North of Cheyenne Wells
Project complete
About the Project
This was a resurfacing and safety improvement project on a 16-mile stretch of U.S. Highway 385 north of Cheyenne Wells. Work included adding up to six inches of new asphalt along the project corridor, repairing a bridge deck, performing full depth reclamation on over three miles of highway, and making other safety improvements.
Project Facts
- Cost: $13.5 Million
- Contractor: A&S Construction
- Timeline: September 2022 to July 2023 with a winter shutdown from December 8, 2022 to April 24, 2023
- Location: US 385
- City: north of Cheyenne Wells
- Mile Points: 172.7 to 156.8
- County: Kit Carson, Cheyenne