US 287 Longmont Intersection Improvements

Project completed

About the Project

Work  is complete, as tTcompleted work on improvements to three intersections along US 287 (Main Street) in Longmont.

This project has improved driving conditions and safety along three stretches of US 287. Work on this project included:

  • adding a lane on northbound US 287 starting at Pike Road and ending 1000 feet south.
  • median work on US 287 at 17th Avenue and at Grand Avenue
  • median work on US 287 at Grand Ave

Duran Excavating, of Greeley, was the prime contractor on this project. Work was completed in mid-September, 2020 

Project Facts

  • Cost: $1.3 million
  • Contractor:  Duran Excavating
  • Timeline: April to August 2020
  • Location: On northbound US 287 from Pike Rd. 1000' south, with median work on US 287 at 17th and Grand Avenue