US 285 south of Saguache

Project Owner CDOT
CDOT Region 5
County Saguache
Description of Work Resurfaces eight miles of US 285 in asphalt.
Estimated Total Project Cost $4,877,871
ARRA Funds $4,779,826
Project Status Construction Complete
Start Date August 27, 2009
Completion Date November 2009
Percentage Spent 100%
Contractor Elam Construction Co.