US 160 & CO 17 Intersection Improvements

About the Project

This project is located at the intersection of U. 160 and CO 17 on the east side of Alamosa. The design includes signalization of the intersection, re-configuration of the existing traffic islands to improve traffic flow, and improvements to pedestrian safety and mobility by adding ADA compliant curbs and ramps.

See the Project Flyer!

Project Facts

  • Cost: $4.5 million
  • Contractor: Concrete Works of Colorado
  • Timeline: July - December 2020
  • Location: Intersection of US 160 and CO 17 on east side of Alamosa

US 160 & CO 17 Project Map

US 160 & CO 17 Work Zone in Alamosa
(Click image to enlarge)



Project Map


Proposed Work Schedule

July through mid-December

  • Normal working hours will be from 7 a.m. to 7 p.m., Monday through Friday. In special cases, these hours may be extended.
  • No weekend work is anticipated

PROJECT SCHEDULE IS SUBJECT TO CHANGE


Traffic Impacts

  • One-lane closures
  • Turn-lane closures
  • Shoulder closures