US 550 Intersection Improvements at 17th, 22nd & 32nd Streets in Durango

Project complete

Project Overview

Crews on this project completed the following work:

  • replaced signals
  • improved the road
  • constructed ramps and sidewalks at each intersection that comply with the Americans with Disabilities Act (ADA)
  • improved storm-drain inlets
  • added and upgrading pavement markings for bike lanes, bike boxes and stop bars at crosswalks
  • added a sidewalk at the small island (the triangle area at the east edge of Fassbinder Park) between 17th Street and West Park Avenue to provide pedestrians refuge at a lengthy crossing
  • replaced a span-wire signal at 22nd Street with new signal heads, poles and mast arms
  • replaced the traffic signal at 32nd Street
  • added and upgraded pavement markings between 32nd Street and East 2nd Avenue to provide two left-turn lanes onto southbound Main Avenue, one shared through/right turn-lane, and a small raised island at the intersection designating a free-flow right turn onto northbound Main Avenue (US 550)

Project Facts

  • Cost: $3.6 million
  • Contractor: Kirkland Construction
  • Timeline: Early October 2018 to Memorial Day 2019
  • Location: Where US Highway 550 (aka, North Main Avenue) intersects with 17th, 22nd and 32nd streets in Durango