US 50 Bridge Repairs Over Agate Creek

Project complete

Project Facts

  • Cost: $1.2 million
  • Contractor: Dietzler Construction
  • Timeline: June to October 2018
  • Location: On US 50 in Saguache County near the Town of Sargents

Project Overview

In October 2018, crews finished replacing a bridge, installing guardrail and paving along US Highway 50, about 10 miles west of Monarch Pass. The project site was at Agate Creek, just east of the Town of Sargents in Saguache County from mile points (MP) 190 to 191.