US 40 Elk Springs Resurfacing
Project Facts
- Cost: $2.4 million
- Contractor: Elam Construction
- Timeline: April to late July 2019
- Location: US 40 west of Craig, from MP 31 to MP 37 near Bear Valley Road (Elk Springs)
US 40 west of Craig
In April 2019, crews resurfaced a six-mile stretch of US 40 west of Craig, near Bear Valley Road (Elk Springs).
The shoulder and guardrail work is now complete and paving operations have been completed.
Schedule & Travel Impacts
- No further impacts