Project Schedule
Below is a tentative schedule for the project:
Start of Construction: Mid-November 2009
First Closure of US 34 at Upper Bridge (milepost 65.4): February 3, 2010 through February 14, 2010 (US 34 reopened on February 10th, four days ahead of schedule)
Second Closure of US 34 at Lower Bridge (milepost 66.3): March 1, 2010 through March 12, 2010 (US 34 reopened on March 8th, four days ahead of schedule)
Construction Complete: March 27, 2010