US 34 from I-25 to Greeley Intelligent Transportation System installation
Project Facts
- Cost: $3 million
- Project Engineer(s): Jill Scott
- Contractor(s): Zayo, Paonia, Fiber Works and Dillie and Kuhn
CDOT has shared its right-of-way and existing infrastructure with Zayo, in exchange for its construction work on this project.
In 2016, crews on this project installed fiber optic cable on US 34 from Greeley to I-25. This work will accommodate the future implementation of the intelligent transportation system (ITS), which will include the use of connected vehicles (aka, driverless cars).