US 287 Intersection Improvements at Foothills Pkwy

Project Facts

  • Cost: $525,000
  • Contractor: Sturgeon Electric
  • Timeline: March -June 2020
  • Location: At intersection of US 287 & Foothills Parkway in Larimer County

US 287 Foothills Map

As part of CDOT’s Whole System Whole Safety initiative, the intersection improvement project will include removing the existing pedestrian curb ramps and replacing them with American’s with Disabilities Act (ADA) ramps providing functional accessibility to all travelers.

Crews will replace the full signal and electronic equipment as well as replace and update all existing accessibility features and pedestrian  curb ramps to bring them into compliance with the Public Right of Way (PROWAG) requirements.  Improvements will also be made to curbs, gutters, and islands.


Work Schedule

  • Motorists can expect a shoulder closure from 7:00 am to 3:30 pm with a
    single lane closure from 8:30 am to 3:30 pm.

Traffic Impacts

  • Motorists can expect single lane and shoulder closures throughout the
    project limits.