US 287 & CO 14 Flood Repairs

Project completed

Project Facts

  • Cost: $934,000
  • Contractor: Duran Excavating
  • Timeline: March to July 2019
  • Locations:
    • CO 14 from mile point (MP) 104.83 to MP 106.26
    • CO 14 from MP 114.04 to MP 106.26; and
    • US 287 at MP 355.10

About the Project

Crews on this project will place erosion-control materials along highway embankments at various locations on US 287 and CO 14, temporarily divert river channel flow, and reconstruct and install cross culverts.  


Traffic Impacts


Crews started this project in March 2019, and expect to complete work in July 2019.

  • Work hours: 7 a.m. to 5 p.m., Monday through Friday
  • Expect traffic restrictions, including:
    • reduced speed limits
    • shoulder and lane closures
    • flaggers on site
    • delays