CO 133 McClure Pass Fault Repairs
Project completed
Project Facts
- Cost: $1.3 million
- Contractor: Anderson Drilling
- Timeline: May - October 2018
- Location: In both directions of CO 133, from mile points 40.54 to 40.61, about five miles south of the Marble turn off
Project Overview
On May 14, 2018, CDOT began reinforcing a fault, aka a rock slip, on Colorado Highway 133—on the south side of McClure Pass—in Gunnison County.
Specific work includes stabilizing and reinforcing a landslide below the roadway to reduce the risk of further slipping or future rockslides. Work items will involve:
- excavating approximately 3,750 tons (or 3,000 cubic yards) of rock material;
- drilling approximately 18, 60-foot-deep caissons, into which vertical and horizontal reinforcing supports (or rebar cages) will be positioned;
- installing rebar cages, a circular set of 18, 60-foot sections of rebar that are 24 inches in diameter;
- constructing a tieback system, which incorporates high-strength steel strand anchors, that are grouted in-place to anchor the vertical caissons.
- repairing and reconstructing the damaged roadway;
- conducting earthwork and erosion control; and
- adding new striping and signage.
Schedule
- Work hours are 7 a.m. to 7 p.m., Monday through Friday.
Travel Impacts
- Through mid-October 2018, travelers can expect single-lane, alternating travel, and periodic full traffic holds of up to 15 minutes.
- Please note: Delays will exceed 15 minutes, as traffic queues must be cleared in each direction.
- There will be a 10-foot width restriction in place during work hours.
- Please avoid distractions when driving through the work zone, and go Slow for the Cone Zone!
Adjacent Projects
This summer/fall, there will two additional (and separate) projects underway on CO 133:
- CO 133 Bowie Resurfacing & Bridge Repair
April 23 through Sept. 30, 2018
Work will be completed between mile points 11.43 and 23.4, south of this project - CO 133 McClure Pass to Redstone Resurfacing
May - September 2018
Work will be complete between mile points 43 and 50, north of this project