Southwestern Colorado Highway Restriping
About the Project
The Colorado Department of Transportation will begin re-striping pavement markings throughout southwest and south-central Colorado. Straight Stripe Painting, Inc. of St. George, UT has been selected for this project. Re-striping operations will begin June 1 and will continue through August, 2020.
Work includes re-striping and replacing existing pavement markings, and enhancing highway striping on both asphalt and concrete pavements. New yellow and white paint will improve visibility and help drivers stay in their lane; this will provide a safer roadway experience and highway system for the traveling public.
Project Schedule
Please note striping operations are dependent on clear weather conditions. The targeted dates may fluctuate.
Southwest Colorado
- June 1-3: US 491 Colorado/New Mexico state line through Cortez and Dove Creek to Colorado/Utah state line
- June 5: US 160 Cortez to Mancos
- June 8 CO 145 Lizard Head Pass from to Mountain Village
- June 10: CO 62 from Placerville to Ridgeway
- June 12-29: US 550 from Colorado/New Mexico state line to Durango, over Red Mountain Pass to Colona
South-central Colorado
- July 1-August 3: US 160 from Mancos through Durango, Pagosa Springs, over Wolf Creek pass to Alamosa
and finishes on La Veta Pass - August 4-5: US 285 from Alder over Poncha Pass to Johnson Village
- August 7-15: US 50 from the CO 114 intersection to Coaldale
- August 17: US 291 from Salida to the US 24 Intersection
- August 18-20: US 24 from Granite to Antero Junction (U.S. 24/U.S 285 intersection)
Project Facts
- Cost: $1.6 Million
- Contractor: Innovative Marking Systems, Inc.
- Timeline: April to October 2020
- Location: Various highways in Southwestern Colorado
Safety Warning
To avoid damaging your vehicle, please drive patiently in the work zone, and do not pass the striping truck and cross over fresh paint. The striping truck will pull over when possible to allow traffic queues to clear.
Traffic Impacts
Travelers will encounter re-striping operations Monday through Saturday, from 7 a.m. to 7 p.m.
- Speeds will be reduced to 40 mph in work zones
- This is a swift moving, mobile operation; although work zones will only be in place for a few hours, motorists are urged to use caution and watch for heavy equipment
- Through lanes and turn lanes may be temporarily closed to traffic causing brief travel delays
- Any temporary closures are to ensure the safety of the workers and the traveling public
- Travelers are discouraged from passing the striping truck and crossing over fresh paint, as this may
damage a vehicle’s finish.