Statewide Fiber Backbone Connection to State Buildings
About the Project
Interface Communications Company will connect numerous state buildings to the fiber backbone network. This project will provide communications between multiple CDOT Maintenance Facilities and CDOT’s Intelligent Transportation Center located in Golden Colorado.
Project Facts
- Cost: $2.1 Million
- Contractor: Interface Communications
- Timeline: October 2021 - July 2021
- Location: Various highways near State buildings in Adams, Arapahoe, Boulder, Clear Creek, Denver, Douglas, Elbert, Jefferson, Kit Carson, Larimer, Lincoln, and Weld counties
Proposed Work Schedule
- Crews will be working Monday through Friday between the hours of 7 a.m. to 5 p.m., or as directed by region lane closure requirements per area
Traffic Impacts
- No width restriction or speed reduction is anticipated
- Travelers can expect the right shoulder of southbound I-25 off-ramp through through right shoulder of southbound on-ramp closed