Southwest Colorado Crack Repairs on US 550, CO 184 and CO 141
Project Facts
- Cost: $386,075
- Contractor(s): A-1 Chipseal Company
- Timeline: spring 2018
In April and May 2018, CDOT repaired segments of US Highway 550, Colorado Highway 184 and Colorado Highway 141.
Over the span of several weeks, crews placed a heated crack sealant into cracks on each highway to improve and prolong their lives.
Work took place at the following dates and locations:
Dates |
Highway |
County/
|
Location
|
April 23-25 | US 550 Durango | La Plata County | 28.20–37.30 |
April 26-May 2 | CO 184B | Mancos & Montezuma counties | 8.9-26.6 |
May 3-4 | US 550 Ridgway | Ouray County | 107-113 |
May 7-10 | CO 141 (Nucla/Naturita) | Montrose County | 74-88 |