Signal Improvements in Florence and Pueblo

Project Facts
 

  • Cost:
    $2.8 million

Project Team

  • Contractor(s): Keci Colorado, Inc.

Crews upgraded traffic signal equipment and performed associated work at the following intersections:

  • CO 67 at CO 115 in Florence (northbound to eastbound turning radius)
  • CO 96 at Grant in Pueblo
  • CO 96 at Court in Pueblo
  • CO 96 at Main Street in Pueblo

This project also improved the following:

  • accessibility to signal poles and crossing intersections
  • pedestrian bump-outs on CO 96 to minimize the distance pedestrians have to walk
  • drainage and utility features

Project work started in March 2016 and was completed in November 2016.